Add to watchlistEmployee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.
Budget (BAC)
Actual cost
94% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Benefits RealizationPhase 11 of 11
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
- Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase
Team & roles
1 member, about 0.0 full-time equivalents
Leadership
1 member
- Dana S. Al-SalehProject manager0%Allocated 120% across all projectsA
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 5 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Sarah A. Al-Qarni
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Sarah A. Al-Qarni | Project sponsor | Decisions and funding | SupportiveLeading | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-09-26 | |||
| Abdulmajeed R. Al-Dosari | Business owner | Accepts deliverables, owns benefits | SupportiveLeading | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-09-29 | |||
| Projects Follow-up Office (EPMO) | Governance | Compliance and data quality | Supportive | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-09-23 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@bog.gov.sa | 2026-09-20 | |||
| Integrated Business Systems Co. | Main vendor | Delivers the contracted work | ResistantSupportive | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-09-30 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-09-02 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingDana S. Al-Saleh2026-10-22
- Business ownerDeliverable status and acceptance datesFortnightlyEmailDana S. Al-Saleh2026-10-10Overdue
- EPMOData and indicator updatesWeeklyDashboardDana S. Al-Saleh2026-10-07
- BeneficiariesWhat changes and whenAt milestonesNewsletterDana S. Al-SalehAt launch
Coming up
By date
- 072026-10EPMODashboard · Weekly
- 102026-10Business ownerEmail · Fortnightly
- 222026-10Project sponsorMeeting · Monthly