PRJ-2026-032On track11Benefits RealizationAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 11.4M split into spent, committed and left, with the estimate at completion

EAC SAR 10.8M
Revised request SAR 11.4M
  • Actual spendSAR 10.8M
  • Committed, not spentSAR 145K
  • Allotted, uncommittedSAR 158K
  • Contingency availableSAR 342K

Budget

Original budgetwhen the first baseline was approved
SAR 11.4M
Approved budgetafter approved change requests
SAR 11.4M
Current budgetavailable to spend now
SAR 11.4M
Revised budgetif the pending changes are approved
SAR 11.4M

Commitments

Commitmentssigned contracts and purchase orders
SAR 10.9M
Contracts1 active contract
SAR 8.8M
Purchase orders⁦0⁩ orders
SAR 2.1M
Remaining budgetapproved less actual
SAR 645K

Spend & outlook

Actual costincluding accruals
SAR 10.8M
Accrualswork done, not yet invoiced
SAR 430K
Estimate at completionthe PM’s bottom-up forecast
SAR 10.8M
ContingencySAR 228K drawn of SAR 570K
SAR 342K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 228K drawn of SAR 570K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 228K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.880.870.860.85⁦+0.04⁩
2Analysis & design1.881.851.831.80⁦+0.08⁩
3Build4.424.364.304.23⁦+0.19⁩
4Testing & acceptance2.212.182.152.12⁦+0.09⁩
5Launch & handover1.661.641.611.59⁦+0.07⁩
Unallocated contingency0.340.000.000.17⁦+0.17⁩
Total11.4010.9010.7610.76⁦+0.65⁩

Budget split

WBS

SAR 11.4M

Budget

  • Management & governanceSAR 884.6K⁦8%⁩
  • Analysis & designSAR 1.9M⁦16%⁩
  • BuildSAR 4.4M⁦39%⁩
  • Testing & acceptanceSAR 2.2M⁦19%⁩
  • Launch & handoverSAR 1.7M⁦15%⁩
  • Unallocated contingencySAR 342K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2025-09-30⁩

SPI(t) ⁦1.00⁩ against the approved finish ⁦2025-09-30⁩

Planned valuePV
SAR 11.4M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 11.4M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 10.8M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 11.4M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.65⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦+0.00⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.06
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
1.00
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 10.8M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 0
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.65⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 10.8M
  • If the rest goes to planSAR 10.8M
  • At cost and schedule performanceSAR 10.8M
  • The PM’s bottom-up estimateSAR 10.8M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 10.8M

Variance at completion: ⁦+0.65⁩ SAR M