PRJ-2026-032On track11Benefits RealizationAgile
HR Self-Service
Add to watchlistEmployee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.
Project managerDana S. Al-SalehSponsorSarah A. Al-QarniProgrammeEnterprise Systems & Archiving Programme
Budget (BAC)
SAR 11.4M
Actual cost
SAR 10.8M
94% of budget
Progress
100%
Planned 100%
Estimate at completion
SAR 10.8M
SPI · CPI
1.00Schedule performance index · 1.001.06Cost performance index · 1.06
Forecast finish
2025-09-21
On baseline
Benefits RealizationPhase 11 of 11
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
- Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work11.1M16 elements
Unallocated contingency342KSAR 570K
Budget at completion11.4MPRJ-2026-032
Weighted progress100%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total100%11.0610.76