HR Self-Service
Add to watchlistEmployee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.
Budget (BAC)
Actual cost
94% of budget
Progress
Planned 100%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Benefits RealizationPhase 11 of 11
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
- Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
- Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
- Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2024-08-28 | 2024-08-26 | −2 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2024-11-24 | 2024-11-21 | −3 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2025-04-06 | 2025-03-31 | −6 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2025-07-04 | 2025-06-26 | −8 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2025-09-30 | 2025-09-21 | −9 days | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline032-D1 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2024-07-15 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting032-D2 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2024-08-28 | V1 | 2 of 2 |
| Deliverable: Business requirements032-D3 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2024-10-11 | V1 | 2 of 2 |
| Deliverable: Solution design032-D4 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2024-11-24 | V1 | 2 of 2 |
| Deliverable: Release 1032-D5 | Approved | Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2025-01-08 | V1 | 2 of 2 |
| Deliverable: Release 2032-D6 | Approved | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | Abdulmajeed R. Al-Dosari | 2025-02-21 | V1 | 2 of 2 |