PRJ-2026-032On track11Benefits RealizationAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩

Planned ⁦100%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

Benefits RealizationPhase ⁦11⁩ of ⁦11⁩

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate17 November 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate31 May 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate15 June 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate26 July 2024Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionConditional goDate20 July 2025Monitoring & Control · CompleteMonitoring & Control · Complete
  9. Gate into «Handover»DecisionGoDate20 August 2025Handover · CompleteHandover · Complete
  10. Gate into «Closure»DecisionConditional goDate30 September 2025Closure · CompleteClosure · Complete
  11. Gate into «Benefits Realization»DecisionGoDate29 November 2025Benefits Realization · Current phaseBenefits Realization · Current phase

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+7

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦100%⁩ done against ⁦100%⁩ planned.

SPI ⁦1.00⁩, CPI ⁦1.06⁩.

Progress & earned value

⁦5⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦96%⁩ of budget

10.8M/ 11.4M645Kprojected saving(⁦5.7%⁩)
Actual spend
10.8M
Committed
10.9M
Approved budget
11.4M
Estimate at completion
10.8M

Next milestones

  • Every milestone is complete

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦4⁩ of ⁦4⁩ approved

  • Project management planDLV-032-1 · V1Dana S. Al-Saleh⁦2024-05-26⁩2024-05-2618 Dhuʻl-Qiʻdah 1445 AHApproved
  • Main deliverable — stage 1DLV-032-2 · V1Abdulmajeed R. Al-Dosari⁦2025-01-22⁩2025-01-2222 Rajab 1446 AHApproved
  • Main deliverable — final stageDLV-032-3 · V1Abdulmajeed R. Al-Dosari⁦2025-07-20⁩2025-07-2025 Muharram 1447 AHApproved
  • Final reportDLV-032-4 · V1Abdulmajeed R. Al-Dosari⁦2025-09-30⁩2025-09-308 Rabiʻ II 1447 AHApproved

Team, contracts & documents

Team

1 member

Dana S. Al-Saleh · Director, Systems & Applications
  • Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsProject managerP-025d.alsaleh@bog.gov.sa⁦0%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled