Change requests, their impact analysis and the CCB approval path.
of 16 this year
session 42 — tomorrow
all open requests
extra days on projects
worth SAR 75M
29 October 2026 · 13:00Meeting Room 3 — 5th floor
Agenda
From submission to the board’s decision — click a stage to filter the list
Cost impact by kind of change
All requests this year
SAR 137.5M
Total
Any change to scope, budget, schedule, deliverables, contract or resources comes through here.
Display options
| Mueen Digital Platform — Release 4 | Resources | +SAR 980K | −12 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Mueen Platform — Release 4P-005s.alghamdi@bog.gov.sa | 2026-10-26 | In 12 days2026-11-0929 Jumada I 1448 AH | 0/6 | Submitted | |
| Mueen Digital Platform — Release 4 | Contract | +SAR 1.2M | None | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Mueen Platform — Release 4P-005s.alghamdi@bog.gov.sa | 2026-10-20 | In 6 days2026-11-0323 Jumada I 1448 AH | — | Submitted | |
CR-2026-014 Re-route the network in Al-Rawdah district | Secure Judicial Network | Scope | +SAR 1.2M | +20 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | 2026-10-19 | In 5 days2026-11-0222 Jumada I 1448 AH | — | Submitted |
CR-2026-004 Add e-filing of appeals to the first release | Mueen Digital Platform — Release 4 | Scope | +SAR 1.9M | +21 d | Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Mueen Platform Office & Digital Judicial Services Programme ManagerP-004r.aldosari@bog.gov.sa | 2026-10-15 | Due tomorrow2026-10-2918 Jumada I 1448 AH | 4/6 | In review |
| Board ERP System | Budget | +SAR 6.8M | +45 d | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-10-09 | In 2 days2026-10-3019 Jumada I 1448 AH | 2/6 | In review | |
| Jeddah Administrative Courts Complex | Scope | +SAR 22.5M | +75 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | 2026-10-06 | 1 day overdue2026-10-2716 Jumada I 1448 AH | 0/6 | Submitted | |
CR-2026-006 Extend the contract by 150 days | Riyadh Administrative Court Building | Schedule | — | +150 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | 2026-10-01 | 6 days overdue2026-10-2211 Jumada I 1448 AH | 0/6 | In review |
CR-2026-010 Redesign the foundations of axes 12 to 16 | Buraydah Administrative Courts Complex | Scope | +SAR 8.4M | +55 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-09-28 | 9 days overdue2026-10-198 Jumada I 1448 AH | 4/6 | In review |
| Board of Grievances Mobile App — Release 3 | Deliverables | +SAR 320K | +10 d | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | 2026-09-14 | 2026-09-282026-09-2817 Rabiʻ II 1448 AH | 6/6 | Deferred | |
CR-2026-005 Variation 7: revise the central HVAC system | Riyadh Administrative Court Building | Contract | +SAR 18.6M | +40 d | Eng. Shahad M. Al-MalkiEng. Shahad M. Al-MalkiDirector, Judicial Buildings & PremisesP-022s.almalki@bog.gov.sa | 2026-08-20 | 55 days overdue2026-09-0321 Rabiʻ I 1448 AH | 6/6 | Escalated |
CR-2026-015 Add a classified-correspondence module | Administrative Correspondence & e-Archive Platform | Deliverables | +SAR 650K | +30 d | Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa | 2026-08-11 | 2026-08-252026-08-2512 Rabiʻ I 1448 AH | 6/6 | Rejected |
CR-2026-013 Replace the cooling-unit supplier | Board Backup Data Centre | Contract | +SAR 3.1M | +14 d | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@bog.gov.sa | 2026-05-17 | 2026-05-312026-05-3114 Dhuʻl-Hijjah 1447 AH | 6/6 | Approved |
CR-2026-011 Redesign courtrooms for video hearings | Jeddah Administrative Courts Complex | Scope | +SAR 9.6M | +20 d | Eng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiDirector, Design & Fit-outP-023f.alsulami@bog.gov.sa | 2026-04-12 | 2026-04-262026-04-269 Dhuʻl-Qiʻdah 1447 AH | 6/6 | Approved |
CR-2026-002 Add a third basement level to Building 5 | Board of Grievances Headquarters, Riyadh | Scope | +SAR 38.5M | +60 d | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-03-02 | 2026-03-232026-03-234 Shawwal 1447 AH | 6/6 | Approved |
| Mueen Digital Platform — Release 4 | Scope | +SAR 2.4M | +18 d | Eng. Sultan F. Al-GhamdiEng. Sultan F. Al-GhamdiProject Manager, Mueen Platform — Release 4P-005s.alghamdi@bog.gov.sa | 2026-02-10 | 2026-02-242026-02-247 Ramadan 1447 AH | 6/6 | Approved | |
CR-2026-003 Add a video-hearing courtroom wing | Dammam Administrative Courts Complex — Rehabilitation & Extension | Scope | +SAR 21.4M | +45 d | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | 2026-01-18 | 2026-02-082026-02-0820 Shaʻban 1447 AH | 6/6 | Approved |