PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work32M⁦17⁩ elements
Unallocated contingency990KSAR 1.7M
Budget at completion33MPRJ-2026-026
Weighted progress⁦8%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project637⁦2026-02-01⁩⁦2027-10-31⁩⁦8%⁩32.012.64—
1
Phase267⁦2026-02-01⁩⁦2026-10-26⁩⁦100%⁩1.921.98—
1.1
WBS element166⁦2026-02-01⁩⁦2026-07-17⁩⁦100%⁩0.960.990 / 1
1.2
WBS element163⁦2026-05-16⁩⁦2026-10-26⁩⁦100%⁩0.960.991 / 2
2
Phase267⁦2026-04-24⁩⁦2027-01-16⁩⁦17%⁩3.840.66—
2.1
WBS element231⁦2026-04-24⁩⁦2026-12-11⁩⁦33%⁩1.920.661 / 1
2.2
WBS element58⁦2026-11-19⁩⁦2027-01-16⁩⁦0%⁩1.92—1 / 2
3
Phase130⁦2026-12-25⁩⁦2027-05-04⁩⁦0%⁩12.16——
3.1
WBS element58⁦2026-12-25⁩⁦2027-02-21⁩⁦0%⁩4.05—1 / 1
3.2
WBS element58⁦2027-01-30⁩⁦2027-03-29⁩⁦0%⁩4.05—1 / 1
3.3
WBS element58⁦2027-03-07⁩⁦2027-05-04⁩⁦0%⁩4.05—1 / 2
4
Phase130⁦2027-04-12⁩⁦2027-08-20⁩⁦0%⁩9.60——
4.1
WBS element58⁦2027-04-12⁩⁦2027-06-09⁩⁦0%⁩3.20—1 / 1
4.2
WBS element58⁦2027-05-18⁩⁦2027-07-15⁩⁦0%⁩3.20—1 / 1
4.3
WBS element58⁦2027-06-23⁩⁦2027-08-20⁩⁦0%⁩3.20—1 / 2
5
Phase94⁦2027-07-29⁩⁦2027-10-31⁩⁦0%⁩4.48——
5.1
WBS element58⁦2027-07-29⁩⁦2027-09-25⁩⁦0%⁩2.24—1 / 1
5.2
WBS element58⁦2027-09-03⁩⁦2027-10-31⁩⁦0%⁩2.24—1 / 1
Total⁦8%⁩32.012.64