Energy Retrofit of Existing Court Buildings (ESCO)
Add to watchlistHVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.
Budget (BAC)
Actual cost
8% of budget
Progress
Planned 9%
Estimate at completion
SPI · CPI
Forecast finish
123 days behind baseline
ProcurementPhase 6 of 11
Next gate:Execution24 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
- Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+123 days vs approved
- Critical activities
- 11
- of 14 open activities
- Late activities
- 10
- past their baseline finish
- Schedule performance
- 0.15
- earned ÷ planned value
- Next milestone
- in 80 days
- Designs approved
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 14 open activities, data date 2026-10-28
“Detailed design” needs a pace 8.6× faster than it has kept
It earned 33% in 187 days; the forecast assumes the rest in 44 days. At the pace so far it finishes on 2027-11-12.
Milestones slip 156 days on average
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance