PRJ-2026-026On hold6ProcurementWaterfall

Energy Retrofit of Existing Court Buildings (ESCO)

Add to watchlist

HVAC and lighting retrofits in 34 court buildings through ESCOs on performance contracts.

Budget (BAC)

SAR 33M

Actual cost

SAR 2.6M

⁦8%⁩ of budget

Progress

⁦8%⁩

Planned ⁦9%⁩

Estimate at completion

SAR 33M

SPI · CPI

0.89Schedule performance index · 0.891.00Cost performance index · 1.00

Forecast finish

⁦2027-10-31⁩

123 days behind baseline

ProcurementPhase ⁦6⁩ of ⁦11⁩

Next gate:Execution24 April 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate15 August 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 December 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate1 February 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 February 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate14 March 2026Procurement · Current phaseProcurement · Current phase
  7. Gate into «Execution»DecisionNot held yetDate24 April 2026Execution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+123⁩ days vs approved

Original baseline⁦2027-06-30⁩
Approved baseline⁦2027-06-30⁩
Current forecast⁦2027-10-31⁩
By earned schedule⁦2030-05-22⁩
Critical activities
11
of ⁦14⁩ open activities
Late activities
10
past their baseline finish
Schedule performance
0.15
earned ÷ planned value
Next milestone
in 80 days
Designs approved
Expand allCollapse all
Activity
Energy Retrofit of Existing Court Buildings (ESCO)Planned: ⁦2026-02-01⁩ → ⁦2027-06-30⁩Forecast: ⁦2026-02-01⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-02-01⁩ → ⁦2026-05-18⁩Actual: ⁦2026-02-01⁩ → ⁦2026-10-26⁩
Project plan & baselinePlanned: ⁦2026-02-01⁩ → ⁦2026-04-07⁩Actual: ⁦2026-02-01⁩ → ⁦2026-07-17⁩
Monitoring & reportingPlanned: ⁦2026-03-14⁩ → ⁦2026-05-18⁩Actual: ⁦2026-05-16⁩ → ⁦2026-10-26⁩
Project plan approvedPlanned: ⁦2026-05-18⁩ → ⁦2026-05-18⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Project plan approved
Design & permitsPlanned: ⁦2026-04-24⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-04-24⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
Detailed designPlanned: ⁦2026-04-24⁩ → ⁦2026-06-28⁩Forecast: ⁦2026-04-24⁩ → ⁦2026-12-11⁩Float: ⁦0⁩d+166
Permits & approvalsPlanned: ⁦2026-06-03⁩ → ⁦2026-08-08⁩Forecast: ⁦2026-11-19⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d+161
Designs approvedPlanned: ⁦2026-08-08⁩ → ⁦2026-08-08⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦288⁩dDesigns approved
Civil worksPlanned: ⁦2026-07-14⁩ → ⁦2026-12-08⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-05-04⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2026-07-14⁩ → ⁦2026-09-17⁩Forecast: ⁦2026-12-25⁩ → ⁦2027-02-21⁩Float: ⁦0⁩d+157
StructurePlanned: ⁦2026-08-24⁩ → ⁦2026-10-28⁩Forecast: ⁦2027-01-30⁩ → ⁦2027-03-29⁩Float: ⁦0⁩d+152
FinishesPlanned: ⁦2026-10-04⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-03-07⁩ → ⁦2027-05-04⁩Float: ⁦0⁩d+147
Build completePlanned: ⁦2026-12-08⁩ → ⁦2026-12-08⁩Forecast: ⁦2027-05-04⁩ → ⁦2027-05-04⁩Float: ⁦180⁩dBuild complete
MEP worksPlanned: ⁦2026-11-14⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-08-20⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-11-14⁩ → ⁦2027-01-18⁩Forecast: ⁦2027-04-12⁩ → ⁦2027-06-09⁩Float: ⁦0⁩d+142
InstallationPlanned: ⁦2026-12-24⁩ → ⁦2027-02-28⁩Forecast: ⁦2027-05-18⁩ → ⁦2027-07-15⁩Float: ⁦0⁩d+137
Testing & commissioningPlanned: ⁦2027-02-03⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-06-23⁩ → ⁦2027-08-20⁩Float: ⁦0⁩d+133
Testing & acceptance completePlanned: ⁦2027-04-09⁩ → ⁦2027-04-09⁩Forecast: ⁦2027-08-20⁩ → ⁦2027-08-20⁩Float: ⁦72⁩dTesting & acceptance complete
HandoverPlanned: ⁦2027-03-16⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2027-03-16⁩ → ⁦2027-05-20⁩Forecast: ⁦2027-07-29⁩ → ⁦2027-09-25⁩Float: ⁦0⁩d+128
Final acceptancePlanned: ⁦2027-04-26⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-09-03⁩ → ⁦2027-10-31⁩Float: ⁦0⁩d+123
Final handoverPlanned: ⁦2027-06-30⁩ → ⁦2027-06-30⁩Forecast: ⁦2027-10-31⁩ → ⁦2027-10-31⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦14⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦10⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Detailed design” needs a pace ⁦8.6⁩× faster than it has kept

It earned ⁦33%⁩ in 187 days; the forecast assumes the rest in 44 days. At the pace so far it finishes on ⁦2027-11-12⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 156 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

161
161
147
G1G2G3

The critical chain

In date order, to final acceptance