PRJ-2026-011On track4PlanningWaterfall

Case & Judgment Archive Digitisation

Add to watchlist

Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩

Planned ⁦6%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval1 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Case & Judgment Archive Digitisation

APPROVEDV2Approved ⁦2026-07-03⁩

1Project identity

Project name
Case & Judgment Archive Digitisation
Project code
PRJ-2026-011
Sponsor
Sarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.sa
Project manager
Dana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.sa
Business owner
Munirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.sa
Portfolio & programme
Technology & Enterprise Systems PortfolioEnterprise Systems & Archiving Programme
Type & methodology
IT · Waterfall
Current phase
4Planning

2Background & rationale

Scan ⁦4.2⁩ million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

3Objectives

  1. 1Improve financial planning and diversify revenue

4Scope

In scope

  • Scan ⁦4.2⁩ million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.
  • Migration from legacy systems
  • ERP integration

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Migration from legacy systems
  2. 2ERP integration
  3. 3Essential cybersecurity controls

6Deliverables

1Project management plan⁦2026-07-27⁩
2Main deliverable — stage 1⁦2027-04-08⁩
3Main deliverable — final stage⁦2027-10-15⁩
4Final report⁦2027-12-30⁩

7Key milestones

  1. Charter approved⁦2026-07-03⁩
  2. Contract signed⁦2026-09-30⁩
  3. 50% of works complete⁦2027-04-08⁩
  4. Provisional acceptance⁦2027-11-17⁩
  5. Closure⁦2027-12-30⁩

8Budget

  • Main contract⁦72.1%⁩17.3M
  • Supervision & consulting⁦13.8%⁩3.3M
  • Internal team⁦9.2%⁩2.2M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩1.2M
The owning sector’s approved budgetTotal24M

9Timeline

Start
2026-07-0520 Muharram 1448 AH
Baseline finish
2027-12-302 Shaʻban 1449 AH
Duration
⁦18⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board