Original
Original baseline
- Finish
- 2027-12-30
- Budget
- SAR 24M
- 16 activities
Approved with the project plan at the planning gate.
Approved 2026-07-05 · by Sarah A. Al-Qarni
Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.
Budget (BAC)
Actual cost
6% of budget
Progress
Planned 6%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningPhase 4 of 11
Next gate:Approval1 August 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2026-07-05 · by Sarah A. Al-Qarni
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Dana S. Al-Saleh
What changed from version A to version B
Finish
2027-12-302028-01-04
+5 days
Budget
SAR 24MSAR 24M
0.00 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference