PRJ-2026-011On track4PlanningWaterfall

Case & Judgment Archive Digitisation

Add to watchlist

Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩

Planned ⁦6%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval1 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-12-30⁩
    Budget
    SAR 24M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2026-07-05⁩ · by Sarah A. Al-Qarni

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2028-01-04⁩
    ⁦+5⁩ days
    Budget
    SAR 24M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Dana S. Al-Saleh

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-12-30⁩⁦2028-01-04⁩

⁦+5⁩ days

Budget

SAR 24MSAR 24M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2027-012027-072028-01
  • Project plan approved⁦+30⁩
  • Designs approved⁦+25⁩
  • Build complete⁦+16⁩
  • Testing & acceptance complete⁦+11⁩
  • Final handover⁦+5⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.01⁩
  • 2Analysis & design⁦+0.07⁩
  • 3Build⁦+0.63⁩
  • 4Testing & acceptance⁦+0.08⁩
  • 5Launch & handover⁦+0.06⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Dana S. Al-Saleh
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2026-07-05⁩by Sarah A. Al-Qarni