PRJ-2026-011On track4PlanningWaterfall

Case & Judgment Archive Digitisation

Add to watchlist

Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩

Planned ⁦6%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval1 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
3On track
2At risk
0Late
Average delay17 days
Jan 27Apr 27Jul 27Oct 27Jan 28
Contractual
Build completePlanned: ⁦2027-06-26⁩Forecast / actual: ⁦2027-07-12⁩Delay: 16 daysG3 +16
Executive
Project plan approvedPlanned: ⁦2026-11-04⁩Forecast / actual: ⁦2026-12-04⁩Delay: 30 daysG1 +30
Payment
Final handoverPlanned: ⁦2027-12-30⁩Forecast / actual: ⁦2028-01-04⁩Delay: 5 daysG5 +5
Regulatory
Testing & acceptance completePlanned: ⁦2027-09-27⁩Forecast / actual: ⁦2027-10-08⁩Delay: 11 daysG4 +11
Project
Designs approvedPlanned: ⁦2027-02-05⁩Forecast / actual: ⁦2027-03-02⁩Delay: 25 daysG2 +25

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-11-04⁩⁦2026-12-04⁩⁦+30⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAt risk0Not requested
Designs approvedMS-G2Project⁦2027-02-05⁩⁦2027-03-02⁩⁦+25⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-06-26⁩⁦2027-07-12⁩⁦+16⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saOn track0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-09-27⁩⁦2027-10-08⁩⁦+11⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saOn track0Not requested
Final handoverMS-G5Payment⁦2027-12-30⁩⁦2028-01-04⁩⁦+5⁩ daysDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline011-D1ApprovedDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saMunirah A. Al-Khalidi⁦2026-09-18⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting011-D2Under reviewMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.saMunirah A. Al-Khalidi⁦2026-11-04⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Business requirements011-D3DraftMunirah A. Al-KhalidiMunirah A. Al-KhalidiDirector General, Financial AffairsP-018m.alkhalidi@bog.gov.saMunirah A. Al-Khalidi⁦2026-12-21⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Solution design011-D4DraftSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saMunirah A. Al-Khalidi⁦2027-02-05⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Release 1011-D5DraftSarah A. Al-QarniSarah A. Al-QarniVice President, Executive AffairsP-012s.alqarni@bog.gov.saMunirah A. Al-Khalidi⁦2027-03-24⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Release 2011-D6DraftDana S. Al-SalehDana S. Al-SalehDirector, Systems & ApplicationsP-025d.alsaleh@bog.gov.saMunirah A. Al-Khalidi⁦2027-05-10⁩V0⁦0⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩