PRJ-2026-011On track4PlanningWaterfall

Case & Judgment Archive Digitisation

Add to watchlist

Scan 4.2 million pages of paper case files and judgments, index them automatically and link them to the case records in Mueen.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩

Planned ⁦6%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningPhase ⁦4⁩ of ⁦11⁩

Next gate:Approval1 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate16 January 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current phasePlanning · Current phase
  5. Gate into «Approval»DecisionNot held yetDate1 August 2026Approval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 24M split into spent, committed and left, with the estimate at completion

EAC SAR 24M
Revised request SAR 24M
  • Actual spendSAR 1.4M
  • Committed, not spentSAR 460K
  • Allotted, uncommittedSAR 21.4M
  • Contingency availableSAR 720K

Budget

Original budgetwhen the first baseline was approved
SAR 24M
Approved budgetafter approved change requests
SAR 24M
Current budgetavailable to spend now
SAR 24M
Revised budgetif the pending changes are approved
SAR 24M

Commitments

Commitmentssigned contracts and purchase orders
SAR 1.9M
Contracts0 active contracts
SAR 0
Purchase orders⁦0⁩ orders
SAR 1.9M
Remaining budgetapproved less actual
SAR 22.6M

Spend & outlook

Actual costincluding accruals
SAR 1.4M
Accrualswork done, not yet invoiced
SAR 58K
Estimate at completionthe PM’s bottom-up forecast
SAR 24M
ContingencySAR 480K drawn of SAR 1.2M
SAR 720K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 480K drawn of SAR 1.2M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 480K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.861.451.441.87⁦−0.01⁩
2Analysis & design3.960.080.004.02⁦−0.07⁩
3Build9.310.200.009.47⁦−0.15⁩
4Testing & acceptance4.660.100.004.73⁦−0.08⁩
5Launch & handover3.490.070.003.55⁦−0.06⁩
Unallocated contingency0.720.000.000.36⁦+0.36⁩
Total24.001.901.4424.00⁦+0.00⁩

Budget split

WBS

SAR 24M

Budget

  • Management & governanceSAR 1.9M⁦8%⁩
  • Analysis & designSAR 4M⁦16%⁩
  • BuildSAR 9.3M⁦39%⁩
  • Testing & acceptanceSAR 4.7M⁦19%⁩
  • Launch & handoverSAR 3.5M⁦15%⁩
  • Unallocated contingencySAR 720K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-10-03⁩+278

SPI(t) ⁦0.66⁩ against the approved finish ⁦2027-12-30⁩

Planned valuePV
SAR 3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 1.4M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 1.4M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 24M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.59⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.48
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 24M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 22.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 24M
  • If the rest goes to planSAR 24M
  • At cost and schedule performanceSAR 48.9M
  • The PM’s bottom-up estimateSAR 24M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 24M

Variance at completion: ⁦+0.00⁩ SAR M