PRJ-2026-010On track7ExecutionConstruction

Solar Power for Court Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 court and Board buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work93.1M⁦17⁩ elements
Unallocated contingency2.9MSAR 4.8M
Budget at completion96MPRJ-2026-010
Weighted progress⁦58%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project789⁦2025-03-02⁩⁦2027-04-30⁩⁦58%⁩93.1255.13—
1
Phase207⁦2025-03-02⁩⁦2025-09-25⁩⁦100%⁩5.595.70—
1.1
WBS element127⁦2025-03-02⁩⁦2025-07-07⁩⁦100%⁩2.792.850 / 1
1.2
WBS element127⁦2025-05-21⁩⁦2025-09-25⁩⁦100%⁩2.792.851 / 2
2
Phase207⁦2025-08-08⁩⁦2026-03-03⁩⁦100%⁩11.1711.41—
2.1
WBS element128⁦2025-08-08⁩⁦2025-12-14⁩⁦100%⁩5.595.701 / 1
2.2
WBS element127⁦2025-10-27⁩⁦2026-03-03⁩⁦100%⁩5.595.701 / 2
3
Phase285⁦2026-01-14⁩⁦2026-10-26⁩⁦100%⁩35.3936.12—
3.1
WBS element128⁦2026-01-14⁩⁦2026-05-22⁩⁦100%⁩11.8012.041 / 1
3.2
WBS element127⁦2026-04-04⁩⁦2026-08-09⁩⁦100%⁩11.8012.041 / 1
3.3
WBS element125⁦2026-06-23⁩⁦2026-10-26⁩⁦100%⁩11.8012.041 / 2
4
Phase295⁦2026-05-14⁩⁦2027-03-05⁩⁦7%⁩27.941.90—
4.1
WBS element247⁦2026-05-14⁩⁦2027-01-16⁩⁦20%⁩9.311.901 / 1
4.2
WBS element38⁦2027-01-02⁩⁦2027-02-09⁩⁦0%⁩9.31—1 / 1
4.3
WBS element38⁦2027-01-26⁩⁦2027-03-05⁩⁦0%⁩9.31—1 / 2
5
Phase70⁦2027-02-19⁩⁦2027-04-30⁩⁦0%⁩13.04——
5.1
WBS element38⁦2027-02-19⁩⁦2027-03-29⁩⁦0%⁩6.52—1 / 1
5.2
WBS element38⁦2027-03-15⁩⁦2027-04-22⁩⁦0%⁩6.52—1 / 1
Total⁦58%⁩93.1255.13