PRJ-2026-010On track7ExecutionConstruction

Solar Power for Court Buildings

Add to watchlist

18 MW of rooftop and carport solar across 64 court and Board buildings.

Budget (BAC)

SAR 96M

Actual cost

SAR 55.1M

⁦57%⁩ of budget

Progress

⁦58%⁩

Planned ⁦57%⁩

Estimate at completion

SAR 95.1M

SPI · CPI

1.02Schedule performance index · 1.021.01Cost performance index · 1.01

Forecast finish

⁦2027-04-22⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control10 January 2027

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate13 September 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate1 January 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionConditional goDate2 March 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate10 April 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate4 May 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate6 July 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate10 January 2027Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Original baseline⁦2027-04-30⁩
Approved baseline⁦2027-04-30⁩
Current forecast⁦2027-04-30⁩
By earned schedule⁦2028-03-02⁩
Critical activities
1
of ⁦7⁩ open activities
Late activities
4
past their baseline finish
Schedule performance
0.67
earned ÷ planned value
Next milestone
in 128 days
Testing & acceptance complete
Expand allCollapse all
Activity
Solar Power for Court BuildingsPlanned: ⁦2025-03-02⁩ → ⁦2027-04-30⁩Forecast: ⁦2025-03-02⁩ → ⁦2027-04-30⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-03-02⁩ → ⁦2025-08-12⁩Actual: ⁦2025-03-02⁩ → ⁦2025-09-25⁩
Project plan & baselinePlanned: ⁦2025-03-02⁩ → ⁦2025-06-10⁩Actual: ⁦2025-03-02⁩ → ⁦2025-07-07⁩
Monitoring & reportingPlanned: ⁦2025-05-04⁩ → ⁦2025-08-12⁩Actual: ⁦2025-05-21⁩ → ⁦2025-09-25⁩
Project plan approvedPlanned: ⁦2025-08-12⁩ → ⁦2025-08-12⁩Actual: ⁦2025-09-25⁩ → ⁦2025-09-25⁩Project plan approved
Design & permitsPlanned: ⁦2025-07-05⁩ → ⁦2025-12-15⁩Actual: ⁦2025-08-08⁩ → ⁦2026-03-03⁩
Detailed designPlanned: ⁦2025-07-05⁩ → ⁦2025-10-13⁩Actual: ⁦2025-08-08⁩ → ⁦2025-12-14⁩
Permits & approvalsPlanned: ⁦2025-09-06⁩ → ⁦2025-12-15⁩Actual: ⁦2025-10-27⁩ → ⁦2026-03-03⁩
Designs approvedPlanned: ⁦2025-12-15⁩ → ⁦2025-12-15⁩Actual: ⁦2026-03-03⁩ → ⁦2026-03-03⁩Designs approved
Civil worksPlanned: ⁦2025-11-07⁩ → ⁦2026-06-21⁩Actual: ⁦2026-01-14⁩ → ⁦2026-10-26⁩
Site works & excavationPlanned: ⁦2025-11-07⁩ → ⁦2026-02-16⁩Actual: ⁦2026-01-14⁩ → ⁦2026-05-22⁩
StructurePlanned: ⁦2026-01-09⁩ → ⁦2026-04-19⁩Actual: ⁦2026-04-04⁩ → ⁦2026-08-09⁩
FinishesPlanned: ⁦2026-03-13⁩ → ⁦2026-06-21⁩Actual: ⁦2026-06-23⁩ → ⁦2026-10-26⁩
Build completePlanned: ⁦2026-06-21⁩ → ⁦2026-06-21⁩Actual: ⁦2026-10-26⁩ → ⁦2026-10-26⁩Build complete
MEP worksPlanned: ⁦2026-05-14⁩ → ⁦2026-12-26⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-03-05⁩Float: ⁦8⁩d
SupplyPlanned: ⁦2026-05-14⁩ → ⁦2026-08-23⁩Forecast: ⁦2026-05-14⁩ → ⁦2027-01-16⁩Float: ⁦8⁩d+146
InstallationPlanned: ⁦2026-07-16⁩ → ⁦2026-10-24⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-02-09⁩Float: ⁦8⁩d+108
Testing & commissioningPlanned: ⁦2026-09-17⁩ → ⁦2026-12-26⁩Forecast: ⁦2027-01-26⁩ → ⁦2027-03-05⁩Float: ⁦8⁩d+69
Testing & acceptance completePlanned: ⁦2026-12-26⁩ → ⁦2026-12-26⁩Forecast: ⁦2027-03-05⁩ → ⁦2027-03-05⁩Float: ⁦56⁩dTesting & acceptance complete
HandoverPlanned: ⁦2026-11-18⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-04-30⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-11-18⁩ → ⁦2027-02-26⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-03-29⁩Float: ⁦8⁩d+31
Final acceptancePlanned: ⁦2027-01-20⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-03-15⁩ → ⁦2027-04-22⁩Float: ⁦8⁩d
Final handoverPlanned: ⁦2027-04-30⁩ → ⁦2027-04-30⁩Forecast: ⁦2027-04-30⁩ → ⁦2027-04-30⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦7⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦5⁩ more activities have three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Supply” needs a pace ⁦8.4⁩× faster than it has kept

It earned ⁦20%⁩ in 167 days; the forecast assumes the rest in 80 days. At the pace so far it finishes on ⁦2028-08-26⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 80 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

44
78
127
69
G1G2G3G4

The critical chain

In date order, to final acceptance

Near-critical