Execution Plan for the BOG 2030 Strategy
Add to watchlistTurning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 68%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Closure readiness
Closure planned after the forecast finish on 2026-12-15
A preview of what closure will need, with the planned dates, and the lessons captured so far.
Closure checklist
Seven mandatory items before any project closes.
- 1
Deliverables acceptedNot started
Final acceptance of every deliverable
Dr. Amal F. Al-SudairiPlanned 2026-12-05
- 2
Financial closureNot started
Spend reconciled, commitments closed
Khalid N. Al-MutairiPlanned 2027-01-04
- 3
Contract closureNot started
Contracts closed, retention released
Khalid N. Al-MutairiPlanned 2027-01-14
- 4
Documents archivedNot started
Documents archived with classification
Abeer H. Al-ShamraniPlanned 2027-01-09
- 5
Lessons learnedNot started
Lessons-learned session
Abeer H. Al-ShamraniPlanned 2026-12-30
- 6
Benefits owner assignedNot started
Benefits handed to their owner with a measurement plan
Dr. Amal F. Al-SudairiPlanned 2026-12-25
- 7
Final report approvedNot started
Final report and its approval
Abeer H. Al-ShamraniPlanned 2027-01-19
Post-implementation review
Did it reach its goal? Did it stay on budget? Were the benefits realised? What did we learn and improve?
The review comes after closure
About three months after the forecast finish (2026-12-15), with the sponsor and the benefits owner.
Lessons learned
0 lessons — offered automatically to similar projects when they are created.
No lessons captured yet
Capture what the team learned during delivery; closure needs at least one.
Benefits handover
Each benefit moves from the project manager to an owner who measures it after closure.
No benefits recorded for this project.