PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Team & roles

3 members, about ⁦1.1⁩ full-time equivalents

Leadership

3 members

  • Abeer H. Al-ShamraniProject manager⁦70%⁩A
  • Dr. Mohammed I. Al-SubaieProject sponsor⁦25%⁩R
  • Dr. Noura M. Al-OtaibiGovernance adviser to the BOG 2030 execution plan⁦10%⁩Allocated ⁦105%⁩ across all projectsR

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦5⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Dr. Mohammed I. Al-SubaieManage closelyDr. Amal F. Al-SudairiManage closelyProjects Follow-up Office (EPMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedDar Al-Mashura Management ConsultingManage closely

Interest

Project sponsor

Dr. Mohammed I. Al-Subaie

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-10-21⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Dr. Mohammed I. Al-SubaieProject sponsorDecisions and fundingSupportiveLeadingAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa⁦2026-10-21⁩
Dr. Amal F. Al-SudairiBusiness ownerAccepts deliverables, owns benefitsSupportiveLeadingAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa⁦2026-10-24⁩
Projects Follow-up Office (EPMO)GovernanceCompliance and data qualitySupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa⁦2026-10-18⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@bog.gov.sa⁦2026-10-15⁩
Dar Al-Mashura Management ConsultingMain vendorDelivers the contracted workNeutralSupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa⁦2026-10-25⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa⁦2026-09-27⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingAbeer H. Al-Shamrani⁦2026-11-16⁩
  • Business ownerDeliverable status and acceptance datesFortnightlyEmailAbeer H. Al-Shamrani⁦2026-11-04⁩
  • EPMOData and indicator updatesWeeklyDashboardAbeer H. Al-Shamrani⁦2026-11-01⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterAbeer H. Al-ShamraniAt launch

Coming up

By date

  1. 012026-11EPMODashboard · Weekly
  2. 042026-11Business ownerEmail · Fortnightly
  3. 162026-11Project sponsorMeeting · Monthly