PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 3.2M split into spent, committed and left, with the estimate at completion

EAC SAR 3.2M
Revised request SAR 3.2M
  • Actual spendSAR 2.2M
  • Committed, not spentSAR 760K
  • Allotted, uncommittedSAR 104K
  • Contingency availableSAR 96K

Budget

Original budgetwhen the first baseline was approved
SAR 3.2M
Approved budgetafter approved change requests
SAR 3.2M
Current budgetavailable to spend now
SAR 3.2M
Revised budgetif the pending changes are approved
SAR 3.2M

Commitments

Commitmentssigned contracts and purchase orders
SAR 3M
Contracts1 active contract
SAR 2.9M
Purchase orders⁦0⁩ orders
SAR 100K
Remaining budgetapproved less actual
SAR 960K

Spend & outlook

Actual costincluding accruals
SAR 2.2M
Accrualswork done, not yet invoiced
SAR 90K
Estimate at completionthe PM’s bottom-up forecast
SAR 3.2M
ContingencySAR 64K drawn of SAR 160K
SAR 96K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 64K drawn of SAR 160K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 64K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.310.320.320.32⁦−0.01⁩
2Diagnosis0.620.640.640.64⁦−0.02⁩
3Design0.930.960.960.96⁦−0.03⁩
4Implementation0.930.830.320.93⁦+0.01⁩
5Handover & knowledge transfer0.310.260.000.31⁦+0.00⁩
Unallocated contingency0.100.000.000.05⁦+0.05⁩
Total3.203.002.243.20⁦+0.00⁩

Budget split

WBS

SAR 3.2M

Budget

  • Management & governanceSAR 310.4K⁦10%⁩
  • DiagnosisSAR 620.8K⁦19%⁩
  • DesignSAR 931.2K⁦29%⁩
  • ImplementationSAR 931.2K⁦29%⁩
  • Handover & knowledge transferSAR 310.4K⁦10%⁩
  • Unallocated contingencySAR 96K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-01-24⁩+40

SPI(t) ⁦0.85⁩ against the approved finish ⁦2026-12-15⁩

Planned valuePV
SAR 2.7M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 2.2M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 2.2M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 3.2M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.46⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.83
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 3.2M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 960K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 3.2M
  • If the rest goes to planSAR 3.2M
  • At cost and schedule performanceSAR 3.4M
  • The PM’s bottom-up estimateSAR 3.2M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 3.2M

Variance at completion: ⁦+0.00⁩ SAR M