Execution Plan for the BOG 2030 Strategy
Add to watchlistTurning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.
Budget (BAC)
Actual cost
70% of budget
Progress
Planned 68%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control13 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Execution. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate14 November 2025All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate4 March 2026All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate3 May 2026All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate14 May 2026All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate21 May 2026All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionGoDate8 June 2026All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026ExecutionCurrent phaseCurrent phase
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Operational readiness gate — into hypercare & monitoring
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 1 required document not approved
Checklist
5 of 7 done
- All in-scope services builtMandatory
- User acceptance testing passedMandatory
- Penetration test passed — no critical/high findingsMandatory
- Data migrated and reconciledMandatory
- Operations & support plan, SLAMandatory
- Users trained — judges, clerks and staff
- Launch rollback plan
Required documents
3 of 4 approved
- UAT reportApproved · V1
- Penetration test reportApproved · V1
- Operations & support planSubmitted — awaiting acceptance · V1
- Data migration reconciliationApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Deliverables completeweight 30%Met
Awaiting evidence from the project team.
Quality & securityweight 30%Met
Awaiting evidence from the project team.
Operations & support readinessweight 20%Met
Awaiting evidence from the project team.
User & change readinessweight 20%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Dr. Mohammed I. Al-SubaieProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Dr. Amal F. Al-SudairiBusiness ownerVote pending