PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Scope statement

What the project delivers, what it does not, and when a deliverable counts as accepted.

Turning the Board of Grievances ⁦2030⁩ strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision ⁦2030⁩.

In scope

  • Turning the Board of Grievances ⁦2030⁩ strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision ⁦2030⁩.
  • An approved method
  • Workshops with every sector

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the business owner
  • Main deliverable — final stageMeets the approved specification, signed off by the business owner

Scope baseline

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2026-05-13⁩

    Baseline approved at the planning gate

    Budget3.2MFinish⁦2026-12-15⁩

Requirements register

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business2
  • Functional2
  • Technical0
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦50%⁩

3/6 · test result is a pass

Accepted

⁦50%⁩

3/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-028-01Actionable deliverablesBusinessMustIn progressDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saSB-1
REQ-028-02An approved methodFunctionalMustIn progressAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saSB-1
REQ-028-03Workshops with every sectorFunctionalMustApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saSB-1
REQ-028-04Knowledge transferBusinessCouldIn progressAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saSB-1
REQ-028-05National guidelinesRegulatoryShouldIn progressDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saSB-1
REQ-028-06Data confidentialitySecurityShouldIn progressAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrix

Requirement → deliverable → task → test → acceptance. No requirement has a gap.