PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-12-15⁩
    Budget
    SAR 3.2M
    ⁦15⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2026-05-03⁩ · by Dr. Mohammed I. Al-Subaie

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-12-15⁩
    Budget
    SAR 3.2M
    ⁦15⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Abeer H. Al-Shamrani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-12-15⁩⁦2026-12-15⁩

⁦0⁩ days

Budget

SAR 3.2MSAR 3.2M

⁦0.00⁩ SAR M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-072027-01
  • Project plan approved⁦+15⁩
  • Designs approved⁦+26⁩
  • Build complete⁦+35⁩
  • Testing & acceptance complete⁦+20⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.01⁩
  • 2Diagnosis⁦+0.02⁩
  • 3Design⁦+0.09⁩
  • 4Implementation⁦−0.01⁩
  • 5Handover & knowledge transfer⁦−0.00⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Abeer H. Al-Shamrani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2026-05-03⁩by Dr. Mohammed I. Al-Subaie