PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Execution Plan for the BOG 2030 Strategy

APPROVEDV2Approved ⁦2026-05-01⁩

1Project identity

Project name
Execution Plan for the BOG 2030 Strategy
Project code
PRJ-2026-028
Sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa
Project manager
Abeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.sa
Business owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.sa
Portfolio & programme
Institutional Excellence & Governance PortfolioInstitutional Excellence & Talent Programme
Type & methodology
Consulting · Waterfall
Current phase
7Execution

2Background & rationale

Turning the Board of Grievances ⁦2030⁩ strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision ⁦2030⁩.

3Objectives

  1. 1Develop the organisational and information environment

4Scope

In scope

  • Turning the Board of Grievances ⁦2030⁩ strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision ⁦2030⁩.
  • An approved method
  • Workshops with every sector

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1An approved method
  2. 2Workshops with every sector
  3. 3Knowledge transfer to the internal team

6Deliverables

1Project management plan⁦2026-05-12⁩
2Main deliverable — stage 1⁦2026-08-26⁩
3Main deliverable — final stage⁦2026-11-13⁩
4Final report⁦2026-12-15⁩

7Key milestones

  1. Charter approved⁦2026-05-01⁩
  2. Contract signed⁦2026-06-08⁩
  3. 50% of works complete⁦2026-08-26⁩
  4. Provisional acceptance⁦2026-11-27⁩
  5. Closure⁦2026-12-15⁩

8Budget

  • Main contract⁦71.9%⁩2.3M
  • Supervision & consulting⁦12.5%⁩400K
  • Internal team⁦9.4%⁩300K
  • Contingency reserve (⁦5%⁩)⁦6.3%⁩200K
The owning sector’s approved budgetTotal3.2M

9Timeline

Start
2026-05-0316 Dhuʻl-Qiʻdah 1447 AH
Baseline finish
2026-12-156 Rajab 1448 AH
Duration
⁦7⁩ months

10Key risks

  • No risks recorded yet.

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board