PRJ-2026-028On track7ExecutionWaterfall

Execution Plan for the BOG 2030 Strategy

Add to watchlist

Turning the Board of Grievances 2030 strategy into portfolios, initiatives and KPIs, aligned with Saudi Vision 2030.

Budget (BAC)

SAR 3.2M

Actual cost

SAR 2.2M

⁦70%⁩ of budget

Progress

⁦70%⁩

Planned ⁦68%⁩

Estimate at completion

SAR 3.2M

SPI · CPI

1.03Schedule performance index · 1.031.00Cost performance index · 1.00

Forecast finish

⁦2026-12-15⁩

On baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control13 November 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate14 November 2025Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate4 March 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate3 May 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate14 May 2026Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate21 May 2026Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate8 June 2026Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate13 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
2On track
0At risk
0Late
Average delay19 days
Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-09-21⁩Forecast / actual: ⁦2026-10-26⁩Delay: 35 daysG3 +35
Executive
Project plan approvedPlanned: ⁦2026-06-27⁩Forecast / actual: ⁦2026-07-12⁩Delay: 15 daysG1 +15
Payment
Final handoverPlanned: ⁦2026-12-15⁩Forecast / actual: ⁦2026-12-15⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-02⁩Forecast / actual: ⁦2026-11-22⁩Delay: 20 daysG4 +20
Project
Designs approvedPlanned: ⁦2026-08-09⁩Forecast / actual: ⁦2026-09-04⁩Delay: 26 daysG2 +26

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-06-27⁩⁦2026-07-12⁩⁦+15⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-08-09⁩⁦2026-09-04⁩⁦+26⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-09-21⁩⁦2026-10-26⁩⁦+35⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-11-02⁩⁦2026-11-22⁩⁦+20⁩ daysAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saOn track0Not requested
Final handoverMS-G5Payment⁦2026-12-15⁩⁦2026-12-15⁩On timeAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline028-D1ApprovedAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-06-06⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting028-D2ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-06-27⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Current-state assessment028-D3ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategic Planning & PerformanceP-015a.alsudairi@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-07-19⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Benchmarking028-D4ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-08-09⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Target model028-D5ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-08-30⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Roadmap028-D6ApprovedAbeer H. Al-ShamraniAbeer H. Al-ShamraniHead, Strategic Planning OfficeP-039a.alshamrani@bog.gov.saDr. Amal F. Al-Sudairi⁦2026-09-21⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩