PRJ-2026-020Off track7ExecutionConstruction
Buraydah Administrative Courts Complex
Remove from watchlistA complex for the Qassim administrative and appeal courts, with 30 courtrooms.
Project managerEng. Ahmed Y. AsiriSponsorEng. Turki A. Al-AnaziProgrammeMajor Judicial Complexes Programme
Early warning: 81% chance of slipping within 60 days
Budget (BAC)
SAR 345M
Actual cost
SAR 159.8M
46% of budget
Progress
44%
Planned 55%
Estimate at completion
SAR 363.2M
SAR +18.2M
SPI · CPI
0.80Schedule performance index · 0.800.95Cost performance index · 0.95
Forecast finish
2027-08-03
64 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control29 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work334.7M17 elements
Unallocated contingency10.4MSAR 17.3M
Budget at completion345MPRJ-2026-020
Weighted progress44%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total44%334.65159.79