PRJ-2026-020Off track7ExecutionConstruction

Buraydah Administrative Courts Complex

Remove from watchlist

A complex for the Qassim administrative and appeal courts, with 30 courtrooms.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩

Planned ⁦55%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control29 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+62⁩ days vs approved

Original baseline⁦2027-05-31⁩
Approved baseline⁦2027-05-31⁩
Current forecast⁦2027-08-01⁩
By earned schedule⁦2029-08-30⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.49
earned ÷ planned value
Next milestone
in 132 days
Build complete
Expand allCollapse all
Activity
Buraydah Administrative Courts ComplexPlanned: ⁦2024-06-02⁩ → ⁦2027-05-31⁩Forecast: ⁦2024-06-02⁩ → ⁦2027-08-01⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2024-06-02⁩ → ⁦2025-01-14⁩Actual: ⁦2024-06-02⁩ → ⁦2025-05-14⁩
Project plan & baselinePlanned: ⁦2024-06-02⁩ → ⁦2024-10-19⁩Actual: ⁦2024-06-02⁩ → ⁦2025-01-01⁩
Monitoring & reportingPlanned: ⁦2024-08-28⁩ → ⁦2025-01-14⁩Actual: ⁦2024-10-13⁩ → ⁦2025-05-14⁩
Project plan approvedPlanned: ⁦2025-01-14⁩ → ⁦2025-01-14⁩Actual: ⁦2025-05-14⁩ → ⁦2025-05-14⁩Project plan approved
Design & permitsPlanned: ⁦2024-11-22⁩ → ⁦2025-07-06⁩Actual: ⁦2025-02-23⁩ → ⁦2026-02-03⁩
Detailed designPlanned: ⁦2024-11-22⁩ → ⁦2025-04-10⁩Actual: ⁦2025-02-23⁩ → ⁦2025-09-24⁩
Permits & approvalsPlanned: ⁦2025-02-17⁩ → ⁦2025-07-06⁩Actual: ⁦2025-07-06⁩ → ⁦2026-02-03⁩
Designs approvedPlanned: ⁦2025-07-06⁩ → ⁦2025-07-06⁩Actual: ⁦2026-02-03⁩ → ⁦2026-02-03⁩Designs approved
Civil worksPlanned: ⁦2025-05-15⁩ → ⁦2026-03-23⁩Forecast: ⁦2025-11-04⁩ → ⁦2027-03-09⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2025-05-15⁩ → ⁦2025-10-01⁩Actual: ⁦2025-11-16⁩ → ⁦2026-06-16⁩
StructurePlanned: ⁦2025-08-10⁩ → ⁦2025-12-27⁩Actual: ⁦2026-03-29⁩ → ⁦2026-10-27⁩
FinishesPlanned: ⁦2025-11-04⁩ → ⁦2026-03-23⁩Forecast: ⁦2025-11-04⁩ → ⁦2027-03-09⁩Float: ⁦0⁩d+351
Build completePlanned: ⁦2026-03-23⁩ → ⁦2026-03-23⁩Forecast: ⁦2027-03-09⁩ → ⁦2027-03-09⁩Float: ⁦145⁩dBuild complete
MEP worksPlanned: ⁦2026-01-30⁩ → ⁦2026-12-09⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-06-04⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-01-30⁩ → ⁦2026-06-18⁩Forecast: ⁦2027-02-19⁩ → ⁦2027-04-07⁩Float: ⁦0⁩d+293
InstallationPlanned: ⁦2026-04-27⁩ → ⁦2026-09-13⁩Forecast: ⁦2027-03-20⁩ → ⁦2027-05-06⁩Float: ⁦0⁩d+235
Testing & commissioningPlanned: ⁦2026-07-23⁩ → ⁦2026-12-09⁩Forecast: ⁦2027-04-18⁩ → ⁦2027-06-04⁩Float: ⁦0⁩d+177
Testing & acceptance completePlanned: ⁦2026-12-09⁩ → ⁦2026-12-09⁩Forecast: ⁦2027-06-04⁩ → ⁦2027-06-04⁩Float: ⁦58⁩dTesting & acceptance complete
HandoverPlanned: ⁦2026-10-17⁩ → ⁦2027-05-31⁩Forecast: ⁦2027-05-17⁩ → ⁦2027-08-01⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-10-17⁩ → ⁦2027-03-05⁩Forecast: ⁦2027-05-17⁩ → ⁦2027-07-03⁩Float: ⁦0⁩d+120
Final acceptancePlanned: ⁦2027-01-12⁩ → ⁦2027-05-31⁩Forecast: ⁦2027-06-15⁩ → ⁦2027-08-01⁩Float: ⁦0⁩d+62
Final handoverPlanned: ⁦2027-05-31⁩ → ⁦2027-05-31⁩Forecast: ⁦2027-08-01⁩ → ⁦2027-08-01⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Finishes” needs a pace ⁦51.5⁩× faster than it has kept

It earned ⁦5%⁩ in 358 days; the forecast assumes the rest in 132 days. At the pace so far it finishes on ⁦2045-06-12⁩.

Slippage pattern⁦84%⁩ confidence

Milestones slip 215 days on average — and it is getting worse

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

120
212
351
177
G1G2G3G4