PRJ-2026-020Off track7ExecutionConstruction

Buraydah Administrative Courts Complex

Remove from watchlist

A complex for the Qassim administrative and appeal courts, with 30 courtrooms.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩

Planned ⁦55%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control29 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
2At risk
1Late
Average delay184 days
Jan 25Apr 25Jul 25Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27Jul 27
Contractual
Build completePlanned: ⁦2026-03-23⁩Forecast / actual: ⁦2027-03-09⁩Delay: 351 daysG3 +351
Executive
Project plan approvedPlanned: ⁦2025-01-14⁩Forecast / actual: ⁦2025-05-14⁩Delay: 120 daysG1 +120
Payment
Final handoverPlanned: ⁦2027-05-31⁩Forecast / actual: ⁦2027-08-01⁩Delay: 62 daysG5 +62
Regulatory
Testing & acceptance completePlanned: ⁦2026-12-09⁩Forecast / actual: ⁦2027-06-04⁩Delay: 177 daysG4 +177
Project
Designs approvedPlanned: ⁦2025-07-06⁩Forecast / actual: ⁦2026-02-03⁩Delay: 212 daysG2 +212

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-01-14⁩⁦2025-05-14⁩⁦+120⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-07-06⁩⁦2026-02-03⁩⁦+212⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-03-23⁩⁦2027-03-09⁩⁦+351⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-12-09⁩⁦2027-06-04⁩⁦+177⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-05-31⁩⁦2027-08-01⁩⁦+62⁩ daysEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline020-D1ApprovedEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saEng. Bandar M. Al-Shammari⁦2024-10-19⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting020-D2ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-01-14⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Detailed design020-D3ApprovedEng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-04-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Permits & approvals020-D4ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-07-06⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Site works & excavation020-D5ApprovedEng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-10-01⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Structure020-D6ApprovedEng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.saEng. Bandar M. Al-Shammari⁦2025-12-27⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩