PRJ-2026-020Off track7ExecutionConstruction

Buraydah Administrative Courts Complex

Remove from watchlist

A complex for the Qassim administrative and appeal courts, with 30 courtrooms.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩

Planned ⁦55%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control29 December 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2027-05-31⁩
    Budget
    SAR 345M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2024-06-02⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-08-01⁩
    ⁦+62⁩ days
    Budget
    SAR 353.4M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Ahmed Y. Asiri

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2027-05-31⁩⁦2027-08-01⁩

⁦+62⁩ days

Budget

SAR 345MSAR 353.4M

⁦+8.40⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-012025-072026-012026-072027-012027-07
  • Project plan approved⁦+120⁩
  • Designs approved⁦+212⁩
  • Build complete⁦+351⁩
  • Testing & acceptance complete⁦+177⁩
  • Final handover⁦+62⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+1.73⁩
  • 2Design & permits⁦+3.45⁩
  • 3Civil works⁦+10.21⁩
  • 4MEP works⁦+10.12⁩
  • 5Handover⁦+4.72⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Ahmed Y. Asiri
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2024-06-02⁩by Eng. Turki A. Al-Anazi