Buraydah Administrative Courts Complex
Remove from watchlistA complex for the Qassim administrative and appeal courts, with 30 courtrooms.
Budget (BAC)
Actual cost
46% of budget
Progress
Planned 55%
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control29 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Team & roles
2 members, about 1.0 full-time equivalents
Leadership
1 member
- Eng. Ahmed Y. AsiriProject manager50%Allocated 125% across all projectsA
Vendor team & advisers
1 member
A AccountableR ResponsibleC ConsultedI Informed
Stakeholders
6 stakeholders, 5 of them below the engagement needed
Power / interest matrix
Pick one to see how they are handled
Keep satisfied1
high power, lower interest
Manage closely4
high power and interest
Monitor0
minimal effort
Keep informed1
high interest, lower power
Interest
Project sponsor
Eng. Turki A. Al-Anazi
Decisions and funding
Influence
Interest
Engagement level
Unaware
Resistant
Neutral
Supportive
Leading
A gap of 1 step — needs an engagement plan.
- Impact on the project
- Approves gates and changes
- Engagement plan
- Monthly briefing
Display options
| Organisation | Role | Actions | ||||||
|---|---|---|---|---|---|---|---|---|
| Eng. Turki A. Al-Anazi | Project sponsor | Decisions and funding | SupportiveLeading | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-10-18 | |||
| Eng. Bandar M. Al-Shammari | Business owner | Accepts deliverables, owns benefits | SupportiveLeading | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-10-21 | |||
| Projects Follow-up Office (EPMO) | Governance | Compliance and data quality | Supportive | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-10-15 | |||
| General Directorate of Financial Affairs | Internal department | Payment approval | NeutralSupportive | Haifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@bog.gov.sa | 2026-10-12 | |||
| Al-Bunyan Al-Rasekh Contracting Co. | Main vendor | Delivers the contracted work | NeutralSupportive | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-10-22 | |||
| End beneficiaries | Beneficiaries | Users of the outcome | NeutralSupportive | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Court ComplexesP-020a.asiri@bog.gov.sa | 2026-09-24 |
Communication plan
Who needs what, when, through which channel, and who owns it.
- Project sponsorStatus and decisions neededMonthlyMeetingEng. Ahmed Y. Asiri2026-11-13
- Business ownerDeliverable status and acceptance datesFortnightlyEmailEng. Ahmed Y. Asiri2026-11-01
- EPMOData and indicator updatesWeeklyDashboardEng. Ahmed Y. Asiri2026-10-29
- BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Ahmed Y. AsiriAt launch
Coming up
By date
- 292026-10EPMODashboard · Weekly
- 012026-11Business ownerEmail · Fortnightly
- 132026-11Project sponsorMeeting · Monthly