Buraydah Administrative Courts Complex
Remove from watchlistA complex for the Qassim administrative and appeal courts, with 30 courtrooms.
Budget (BAC)
Actual cost
46% of budget
Progress
Planned 55%
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control29 December 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 December 2023Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate27 July 2024Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate28 August 2024Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionConditional goDate24 November 2024Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate29 December 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+62 days vs approved
- Critical activities
- 7
- of 9 open activities
- Late activities
- 6
- past their baseline finish
- Schedule performance
- 0.49
- earned ÷ planned value
- Next milestone
- in 132 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 9 open activities, data date 2026-10-28
“Finishes” needs a pace 51.5× faster than it has kept
It earned 5% in 358 days; the forecast assumes the rest in 132 days. At the pace so far it finishes on 2045-06-12.
Milestones slip 215 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance