Hail Administrative Court Building
Add to watchlistA new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
Budget (BAC)
Actual cost
53% of budget
Progress
Planned 56%
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth