Hail Administrative Court Building
Add to watchlistA new 18,000 m² building for the Hail administrative court, with 12 courtrooms and a video-hearing suite.
Budget (BAC)
Actual cost
53% of budget
Progress
Planned 56%
Estimate at completion
SAR +3.2M
SPI · CPI
Forecast finish
12 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control20 November 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate27 September 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate21 April 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate12 May 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate8 July 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate20 November 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+11 days vs approved
- Critical activities
- 7
- of 9 open activities
- Late activities
- 6
- past their baseline finish
- Schedule performance
- 0.56
- earned ÷ planned value
- Next milestone
- in 29 days
- Build complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 9 open activities, data date 2026-10-28
“Finishes” needs a pace 4.1× faster than it has kept
It earned 68% in 251 days; the forecast assumes the rest in 29 days. At the pace so far it finishes on 2027-02-23.
Milestones slip 127 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance