Smart Security & Access for Court Buildings
Add to watchlist4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.
Budget (BAC)
Actual cost
84% of budget
Progress
Planned 90%
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control5 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate30 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate19 March 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate7 April 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate27 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate5 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Scope statement
What the project delivers, what it does not, and when a deliverable counts as accepted.
4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.
In scope
- 4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.
- Saudi Building Code compliance
- An approved plan to keep the courts sitting during the works
Out of scope
- Operation and maintenance after the warranty period
- Work outside the approved site or system boundary
Acceptance criteria
- Main deliverable — stage 1Meets the approved specification, signed off by the business owner
- Main deliverable — final stageMeets the approved specification, signed off by the business owner
Scope baseline
Every approved change creates a new baseline
- 1
SB-1Current2025-03-16
Baseline approved at the planning gate
Budget74MFinish2026-10-31
Requirements register
6 requirements of five kinds, with the trace status of each
By type
- Business1
- Functional1
- Technical1
- Regulatory2
- Security1
Fully traced
100%
6/6 · linked to a deliverable, task and test
Test passed
17%
1/6 · test result is a pass
Accepted
17%
1/6 · signed off by the business owner
Display options
| REQ-013-01 | Reach the target number of courtrooms | Business | Must | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-013-02 | Meet the approved technical specs | Technical | Must | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | SB-1 | |
| REQ-013-03 | Courts keep sitting during the works | Functional | Must | In progress | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-013-04 | Saudi Building Code | Regulatory | Should | In progress | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | SB-1 | |
| REQ-013-05 | Civil-defence requirements | Regulatory | Could | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | SB-1 | |
| REQ-013-06 | Site and systems security | Security | Could | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | SB-1 |
Traceability matrix
Requirement → deliverable → task → test → acceptance. No requirement has a gap.