Smart Security & Access for Court Buildings
Add to watchlist4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.
Budget (BAC)
Actual cost
84% of budget
Progress
Planned 90%
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control5 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate30 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate19 March 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate7 April 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate27 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate5 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-06-24 | 2025-08-03 | +40 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-01 | 2025-12-10 | +70 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-26 | 2026-06-21 | +115 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-07-24 | 2026-12-22 | +151 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-10-31 | 2027-01-11 | +72 days | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline013-D1 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2025-05-06 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting013-D2 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2025-06-24 | V1 | 2 of 2 |
| Deliverable: Detailed design013-D3 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2025-08-13 | V1 | 2 of 2 |
| Deliverable: Permits & approvals013-D4 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2025-10-01 | V1 | 2 of 2 |
| Deliverable: Site works & excavation013-D5 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziAssistant President, Projects & FacilitiesP-010t.alanazi@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2025-11-19 | V1 | 2 of 2 |
| Deliverable: Structure013-D6 | Approved | Eng. Waleed O. Al-JuhaniEng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceP-021w.aljuhani@bog.gov.sa | Eng. Bandar M. Al-Shammari | 2026-01-08 | V1 | 2 of 2 |