PRJ-2026-013At risk7ExecutionConstruction

Smart Security & Access for Court Buildings

Add to watchlist

4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 74M

Actual cost

SAR 62.2M

⁦84%⁩ of budget

Progress

⁦79%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 78.7M

SAR +4.7M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control5 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate30 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate19 March 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate7 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate27 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate5 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started