Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-013At risk7ExecutionConstruction

Smart Security & Access for Court Buildings

Add to watchlist

4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 74M

Actual cost

SAR 62.2M

⁦84%⁩ of budget

Progress

⁦79%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 78.7M

SAR +4.7M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionPhase ⁦7⁩ of ⁦11⁩

Next gate:Monitoring & Control5 August 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate30 August 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate19 March 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate7 April 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate27 May 2025Execution · Current phaseExecution · Current phase
  8. Gate into «Monitoring & Control»DecisionNot held yetDate5 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-10-31⁩
    Budget
    SAR 74M
    ⁦17⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-02-16⁩ · by Eng. Turki A. Al-Anazi

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2027-01-11⁩
    ⁦+72⁩ days
    Budget
    SAR 74M
    ⁦17⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Eng. Waleed O. Al-Juhani

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-10-31⁩⁦2027-01-11⁩

⁦+72⁩ days

Budget

SAR 74MSAR 74M

⁦0.00⁩ SAR M

Milestones moved

5 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2025-072026-012026-072027-01
  • Project plan approved⁦+40⁩
  • Designs approved⁦+70⁩
  • Build complete⁦+115⁩
  • Testing & acceptance complete⁦+151⁩
  • Final handover⁦+72⁩

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.42⁩
  • 2Design & permits⁦+0.83⁩
  • 3Civil works⁦+4.12⁩
  • 4MEP works⁦+0.49⁩
  • 5Handover⁦+1.45⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Eng. Waleed O. Al-Juhani
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-02-16⁩by Eng. Turki A. Al-Anazi
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close