Smart Security & Access for Court Buildings
Add to watchlist4,200 cameras and smart entry gates across court buildings, with a central monitoring room and automatic visitor ID checks.
Budget (BAC)
Actual cost
84% of budget
Progress
Planned 90%
Estimate at completion
SAR +4.7M
SPI · CPI
Forecast finish
45 days behind baseline
ExecutionPhase 7 of 11
Next gate:Monitoring & Control5 August 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate30 August 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionConditional goDate19 March 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate7 April 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate27 May 2025Execution · Current phaseExecution · Current phase
- Gate into «Monitoring & Control»DecisionNot held yetDate5 August 2026Monitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+72 days vs approved
- Critical activities
- 4
- of 5 open activities
- Late activities
- 3
- past their baseline finish
- Schedule performance
- 0.79
- earned ÷ planned value
- Next milestone
- in 55 days
- Testing & acceptance complete
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 5 open activities, data date 2026-10-28
“Testing & commissioning” needs a pace 7.4× faster than it has kept
It earned 30% in 175 days; the forecast assumes the rest in 55 days. At the pace so far it finishes on 2027-12-10.
Milestones slip 90 days on average — and it is getting worse
Each milestone’s slip in days, in date order; the later ones slip more than the early ones.
The critical chain
In date order, to final acceptance
Near-critical