Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-008On track8Monitoring & ControlScrum

Khabeer Platform — Release 2

Add to watchlist

A platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover15 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+3

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦91%⁩ done against ⁦90%⁩ planned.

SPI ⁦1.01⁩, CPI ⁦1.02⁩.

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦92%⁩ of budget

16.4M/ 18.4M361Kprojected saving(⁦2.0%⁩)
Actual spend
16.4M
Committed
16.9M
Approved budget
18.4M
Estimate at completion
18M

Next milestones

  • Closure⁦2026-11-26⁩was ⁦2026-11-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & issues

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open issues

⁦0⁩ escalated

  • No open issues

Deliverables

⁦2⁩ of ⁦4⁩ approved

  • Project management planDLV-008-1 · V1Karim Haddad⁦2025-05-27⁩2025-05-2729 Dhuʻl-Qiʻdah 1446 AHApproved
  • Main deliverable — stage 1DLV-008-2 · V1Yousef A. Al-Omari⁦2026-02-22⁩2026-02-225 Ramadan 1447 AHApproved
  • Main deliverable — final stageDLV-008-3 · V1Yousef A. Al-Omari47 days overdue2026-09-1129 Rabiʻ I 1448 AHIn review
  • Final reportDLV-008-4 · V1Yousef A. Al-OmariIn 33 days2026-11-3020 Jumada II 1448 AHIn progress

Team, contracts & documents

Team

4 members

Karim Haddad · Senior Digital Delivery Consultant — EPMOYousef A. Al-Omari · Director General, Partnerships & Revenue DevelopmentEng. Reem K. Al-Dosari · Head of the Mueen Platform Office & Digital Judicial Services Programme Manager
  • Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOProject managerP-041k.haddad@bog.gov.sa⁦30%⁩
  • Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & Revenue DevelopmentOwner of the agency-link procedures, KhabeerP-016y.alomari@bog.gov.sa⁦25%⁩
  • Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the Mueen Platform Office & Digital Judicial Services Programme ManagerProgramme oversight, KhabeerP-004r.aldosari@bog.gov.sa⁦15%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled