Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-008On track8Monitoring & ControlScrum

Khabeer Platform — Release 2

Add to watchlist

A platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover15 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 18.4M split into spent, committed and left, with the estimate at completion

EAC SAR 18M
Revised request SAR 18.4M
  • Actual spendSAR 16.4M
  • Committed, not spentSAR 484K
  • Allotted, uncommittedSAR 948K
  • Contingency availableSAR 552K

Budget

Original budgetwhen the first baseline was approved
SAR 18.4M
Approved budgetafter approved change requests
SAR 18.4M
Current budgetavailable to spend now
SAR 18.4M
Revised budgetif the pending changes are approved
SAR 18.4M

Commitments

Commitmentssigned contracts and purchase orders
SAR 16.9M
Contracts1 active contract
SAR 14.8M
Purchase orders⁦0⁩ orders
SAR 2.1M
Remaining budgetapproved less actual
SAR 2M

Spend & outlook

Actual costincluding accruals
SAR 16.4M
Accrualswork done, not yet invoiced
SAR 657K
Estimate at completionthe PM’s bottom-up forecast
SAR 18M
ContingencySAR 368K drawn of SAR 920K
SAR 552K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 368K drawn of SAR 920K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 368K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance1.431.441.441.44⁦−0.02⁩
2Analysis & design3.033.073.073.07⁦−0.03⁩
3Build7.147.227.227.22⁦−0.08⁩
4Testing & acceptance3.573.613.613.61⁦−0.04⁩
5Launch & handover2.681.571.082.43⁦+0.25⁩
Unallocated contingency0.550.000.000.28⁦+0.28⁩
Total18.4016.9016.4218.04⁦+0.36⁩

Budget split

WBS

SAR 18.4M

Budget

  • Management & governanceSAR 1.4M⁦8%⁩
  • Analysis & designSAR 3M⁦16%⁩
  • BuildSAR 7.1M⁦39%⁩
  • Testing & acceptanceSAR 3.6M⁦19%⁩
  • Launch & handoverSAR 2.7M⁦15%⁩
  • Unallocated contingencySAR 552K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-03-02⁩+92

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-11-30⁩

Planned valuePV
SAR 18.3M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 16.7M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 16.4M
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 18.4M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.33⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.51⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.92
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 18M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 1.6M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.36⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.83
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 18M
  • If the rest goes to planSAR 18.1M
  • At cost and schedule performanceSAR 18.2M
  • The PM’s bottom-up estimateSAR 18M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 18M

Variance at completion: ⁦+0.36⁩ SAR M