Khabeer Platform — Release 2
Add to watchlistA platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.
Budget (BAC)
Actual cost
89% of budget
Progress
Planned 90%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Monitoring & ControlPhase 8 of 11
Next gate:Handover15 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
- Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Monitoring & Control. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate15 November 2024All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate5 March 2025All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionGoDate4 May 2025All criteria and required documents met.InitiationComplete
- Gate into «Approval»DecisionGoDate2 June 2025All criteria and required documents met.PlanningComplete
- Gate into «Procurement»DecisionGoDate19 June 2025All criteria and required documents met.ApprovalComplete
- Gate into «Execution»DecisionGoDate4 August 2025All criteria and required documents met.ProcurementComplete
- Gate into «Monitoring & Control»DecisionGoDate11 September 2026All criteria and required documents met.ExecutionComplete
- Gate into «Handover»DecisionNot held yetDate15 October 2026Monitoring & ControlCurrent phaseCurrent phase
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Handover gate — provisional acceptance
Gate readiness
Meets the pass mark
Automated control: no move until the criteria are met
- 1 mandatory checklist item open
- 1 required document not approved
Checklist
3 of 4 done
- Provisional acceptance certificateMandatory
- Snag list and closure planMandatory
- As-built documents handed overMandatory
- Knowledge transfer to operations
Required documents
1 of 2 approved
- Provisional acceptance certificateNot submitted
- As-built documentationApproved · V1
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Works completeweight 40%Met
Awaiting evidence from the project team.
Open snags acceptableweight 30%Met
Awaiting evidence from the project team.
Operations team readyweight 30%
Awaiting evidence from the project team.
Approvers
Projects Steering Committee
- Dr. Abdullah S. Al-QahtaniSteering Committee chairVote pending
- Dr. Mohammed I. Al-SubaieProject sponsorVote pending
- Dr. Noura M. Al-OtaibiEPMO directorVote pending
- Yousef A. Al-OmariBusiness ownerVote pending