Khabeer Platform — Release 2
Add to watchlistA platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.
Budget (BAC)
Actual cost
89% of budget
Progress
Planned 90%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Monitoring & ControlPhase 8 of 11
Next gate:Handover15 October 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
- Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
- Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
- Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-10 | 2025-09-28 | +18 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-18 | 2026-01-19 | +32 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-16 | 2026-07-07 | +52 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-23 | 2026-10-26 | +64 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2026-11-30 | On time | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Deliverable flow
Display options
| Deliverable: Project plan & baseline008-D1 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Yousef A. Al-Omari | 2025-07-22 | V1 | 2 of 2 |
| Deliverable: Monitoring & reporting008-D2 | Approved | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & Revenue DevelopmentP-016y.alomari@bog.gov.sa | Yousef A. Al-Omari | 2025-09-10 | V1 | 2 of 2 |
| Deliverable: Business requirements008-D3 | Approved | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & Revenue DevelopmentP-016y.alomari@bog.gov.sa | Yousef A. Al-Omari | 2025-10-29 | V1 | 2 of 2 |
| Deliverable: Solution design008-D4 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Yousef A. Al-Omari | 2025-12-18 | V1 | 2 of 2 |
| Deliverable: Release 1008-D5 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.sa | Yousef A. Al-Omari | 2026-02-06 | V1 | 2 of 2 |
| Deliverable: Release 2008-D6 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.sa | Yousef A. Al-Omari | 2026-03-27 | V1 | 2 of 2 |