PRJ-2026-008On track8Monitoring & ControlScrum

Khabeer Platform — Release 2

Add to watchlist

A platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover15 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

4Achieved
1On track
0At risk
0Late
Average delay33 days
Oct 25Jan 26Apr 26Jul 26Oct 26
Contractual
Build completePlanned: ⁦2026-05-16⁩Forecast / actual: ⁦2026-07-07⁩Delay: 52 daysG3 +52
Executive
Project plan approvedPlanned: ⁦2025-09-10⁩Forecast / actual: ⁦2025-09-28⁩Delay: 18 daysG1 +18
Payment
Final handoverPlanned: ⁦2026-11-30⁩Forecast / actual: ⁦2026-11-30⁩G5
Regulatory
Testing & acceptance completePlanned: ⁦2026-08-23⁩Forecast / actual: ⁦2026-10-26⁩Delay: 64 daysG4 +64
Project
Designs approvedPlanned: ⁦2025-12-18⁩Forecast / actual: ⁦2026-01-19⁩Delay: 32 daysG2 +32

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-09-10⁩⁦2025-09-28⁩⁦+18⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-18⁩⁦2026-01-19⁩⁦+32⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-05-16⁩⁦2026-07-07⁩⁦+52⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-08-23⁩⁦2026-10-26⁩⁦+64⁩ daysKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saAchieved1Approved
Final handoverMS-G5Payment⁦2026-11-30⁩⁦2026-11-30⁩On timeKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline008-D1ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saYousef A. Al-Omari⁦2025-07-22⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Monitoring & reporting008-D2ApprovedYousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & Revenue DevelopmentP-016y.alomari@bog.gov.saYousef A. Al-Omari⁦2025-09-10⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Business requirements008-D3ApprovedYousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & Revenue DevelopmentP-016y.alomari@bog.gov.saYousef A. Al-Omari⁦2025-10-29⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Solution design008-D4ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saYousef A. Al-Omari⁦2025-12-18⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 1008-D5ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieDirector General, Decision Support CentreP-009m.alsubaie@bog.gov.saYousef A. Al-Omari⁦2026-02-06⁩V1⁦2⁩ of ⁦2⁩
Deliverable: Release 2008-D6ApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — EPMOP-041k.haddad@bog.gov.saYousef A. Al-Omari⁦2026-03-27⁩V1⁦2⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩