PRJ-2026-008On track8Monitoring & ControlScrum

Khabeer Platform — Release 2

Add to watchlist

A platform to register accredited experts, assign them to cases and follow their reports online until they are filed in the case record.

Budget (BAC)

SAR 18.4M

Actual cost

SAR 16.4M

⁦89%⁩ of budget

Progress

⁦91%⁩

Planned ⁦90%⁩

Estimate at completion

SAR 18M

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

Monitoring & ControlPhase ⁦8⁩ of ⁦11⁩

Next gate:Handover15 October 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate15 November 2024Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionGoDate2 June 2025Approval · CompleteApproval · Complete
  6. Gate into «Procurement»DecisionGoDate19 June 2025Procurement · CompleteProcurement · Complete
  7. Gate into «Execution»DecisionGoDate4 August 2025Execution · CompleteExecution · Complete
  8. Gate into «Monitoring & Control»DecisionGoDate11 September 2026Monitoring & Control · Current phaseMonitoring & Control · Current phase
  9. Gate into «Handover»DecisionNot held yetDate15 October 2026Handover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Baselines

The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.

  1. Original

    Original baseline

    v1.0Approved & lockedVersion A
    Finish
    ⁦2026-11-30⁩
    Budget
    SAR 18.4M
    ⁦16⁩ activities

    Approved with the project plan at the planning gate.

    Approved ⁦2025-05-04⁩ · by Dr. Mohammed I. Al-Subaie

  2. Working

    Working baseline

    v2.0-draftWorking draftVersion B
    Finish
    ⁦2026-11-30⁩
    Budget
    SAR 18.4M
    ⁦16⁩ activities

    Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.

    Created ⁦2026-10-28⁩ · by Karim Haddad

    Edit in the schedule

Compare two versions

What changed from version A to version B

Finish

⁦2026-11-30⁩⁦2026-11-30⁩

⁦0⁩ days

Budget

SAR 18.4MSAR 18.4M

⁦0.00⁩ SAR M

Milestones moved

4 / 5

Milestones: A to B

Each line starts at the milestone’s date in A and ends at its date in B

2026-012026-07
  • Project plan approved⁦+18⁩
  • Designs approved⁦+32⁩
  • Build complete⁦+52⁩
  • Testing & acceptance complete⁦+64⁩
  • Final handover

Version AVersion B

Cost by WBS element

Difference in SAR millions from A to B

  • 1Management & governance⁦+0.02⁩
  • 2Analysis & design⁦+0.03⁩
  • 3Build⁦+0.44⁩
  • 4Testing & acceptance⁦+0.04⁩
  • 5Launch & handover⁦−0.25⁩

Version history

Every saved version with its reason and reference

  1. Working baselinev2.0-draftWorking draftFollows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.⁦2026-10-28⁩by Karim Haddad
  2. Original baselinev1.0Approved & lockedApproved with the project plan at the planning gate.⁦2025-05-04⁩by Dr. Mohammed I. Al-Subaie