Digital Administrative Court HQ, Wadi Al-Dawasir
Add to watchlistA permanent home for the Digital Administrative Court — a video-hearing centre, digital circuit rooms and an edge data centre.
Budget (BAC)
Actual cost
2% of budget
Progress
Planned 2%
Estimate at completion
SPI · CPI
Forecast finish
184 days behind baseline
PlanningPhase 4 of 11
Next gate:Approval13 April 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate12 September 2025Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate31 December 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate1 March 2026Planning · Current phasePlanning · Current phase
- Gate into «Approval»DecisionNot held yetDate13 April 2026Approval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+189 days vs approved
- Critical activities
- 12
- of 17 open activities
- Late activities
- 12
- past their baseline finish
- Schedule performance
- 0.10
- earned ÷ planned value
- Next milestone
- in 110 days
- Project plan approved
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
23 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 17 open activities, data date 2026-10-28
“Project plan & baseline” needs a pace 3.3× faster than it has kept
It earned 67% in 241 days; the forecast assumes the rest in 36 days. At the pace so far it finishes on 2027-02-24.
The critical chain
In date order, to final acceptance
Near-critical