Board of GrievancesMunjaz10My actionsNotifications
PRJ-2026-023On track3InitiationAgile

AI Judicial Assistant

Add to watchlist

An AI assistant that summarises case files, suggests precedents from the judicial codices and helps judges and clerks draft.

Budget (BAC)

SAR 28M

Actual cost

SAR 280K

⁦1%⁩ of budget

Progress

⁦1%⁩

Planned ⁦1%⁩

Estimate at completion

SAR 28M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationPhase ⁦3⁩ of ⁦11⁩

Next gate:Planning6 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
  4. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work27.2M⁦16⁩ elements
Unallocated contingency840KSAR 1.4M
Budget at completion28MPRJ-2026-023
Weighted progress⁦1%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project482⁦2026-09-06⁩⁦2028-01-01⁩⁦1%⁩27.160.28—
1
Phase140⁦2026-09-06⁩⁦2027-01-24⁩⁦13%⁩2.170.28—
1.1
WBS element102⁦2026-09-06⁩⁦2026-12-17⁩⁦25%⁩1.090.280 / 1
1.2
WBS element61⁦2026-11-24⁩⁦2027-01-24⁩⁦0%⁩1.09—1 / 2
2
Phase99⁦2027-01-01⁩⁦2027-04-10⁩⁦0%⁩4.62——
2.1
WBS element61⁦2027-01-01⁩⁦2027-03-03⁩⁦0%⁩2.31—1 / 1
2.2
WBS element61⁦2027-02-08⁩⁦2027-04-10⁩⁦0%⁩2.31—1 / 2
3
Phase137⁦2027-03-18⁩⁦2027-08-02⁩⁦0%⁩10.86——
3.1
WBS element61⁦2027-03-18⁩⁦2027-05-18⁩⁦0%⁩3.62—1 / 1
3.2
WBS element61⁦2027-04-25⁩⁦2027-06-25⁩⁦0%⁩3.62—1 / 1
3.3
WBS element61⁦2027-06-02⁩⁦2027-08-02⁩⁦0%⁩3.62—1 / 2
4
Phase99⁦2027-07-10⁩⁦2027-10-17⁩⁦0%⁩5.43——
4.1
WBS element61⁦2027-07-10⁩⁦2027-09-09⁩⁦0%⁩2.72—1 / 1
4.2
WBS element61⁦2027-08-17⁩⁦2027-10-17⁩⁦0%⁩2.72—1 / 2
5
Phase99⁦2027-09-24⁩⁦2028-01-01⁩⁦0%⁩4.07——
5.1
WBS element61⁦2027-09-24⁩⁦2027-11-24⁩⁦0%⁩2.04—1 / 1
5.2
WBS element61⁦2027-11-01⁩⁦2028-01-01⁩⁦0%⁩2.04—1 / 1
Total⁦1%⁩27.160.28
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close