Analytics & AI Platform
Add to watchlistA unified data platform to run AI models that forecast demand for services.
Budget (BAC)
Actual cost
1% of budget
Progress
Planned 1%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
InitiationPhase 3 of 11
Next gate:Planning6 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
- Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
- Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Project lifecycle and its gates
Current phase: Initiation. Pick a gate on the track to review it.
- Gate into «Feasibility»DecisionGoDate20 March 2026All criteria and required documents met.IdeaComplete
- Gate into «Initiation»DecisionGoDate8 July 2026All criteria and required documents met.FeasibilityComplete
- Gate into «Planning»DecisionNot held yetDate6 September 2026InitiationCurrent phaseCurrent phase
- Gate into «Approval»DecisionNot held yet4PlanningNot started
- Gate into «Procurement»DecisionNot held yet5ApprovalNot started
- Gate into «Execution»DecisionNot held yet6ProcurementNot started
- Gate into «Monitoring & Control»DecisionNot held yet7ExecutionNot started
- Gate into «Handover»DecisionNot held yet8Monitoring & ControlNot started
- Gate into «Closure»DecisionNot held yet9HandoverNot started
- Gate into «Benefits Realization»DecisionNot held yet10ClosureNot started
- 11Benefits RealizationNot started
Initiation gate — charter approved
Gate readiness
Enough for a conditional go only
Automated control: no move until the criteria are met
- 2 mandatory checklist items open
- 2 required documents not approved
- 1 mandatory criteria under 70 points
- Weighted score 70 under the pass mark 75
Checklist
2 of 4 done
- Sponsor and PM appointedMandatory
- Charter approvedMandatory
- Key stakeholders identifiedMandatory
- Governance structure and committees
Required documents
0 of 2 approved
- Project charterSubmitted — awaiting acceptance · V1
- Stakeholder registerNot submitted
Criteria and score
Go from 75, conditional from 60; a mandatory criterion is met from 70.
Charter completenessweight 40%Not met
Awaiting evidence from the project team.
Sponsor and owner commitmentweight 35%Met
Awaiting evidence from the project team.
Team readinessweight 25%
Awaiting evidence from the project team.
Approvers
PMO Committee
- Dr. Noura M. Al-OtaibiPMO directorVote pending
- Eng. Majed S. Al-RasheedProject sponsorVote pending
- Faisal A. Al-ShehriBusiness ownerVote pending