PRJ-2026-023On track3InitiationAgile

Analytics & AI Platform

Add to watchlist

A unified data platform to run AI models that forecast demand for services.

Budget (BAC)

SAR 28M

Actual cost

SAR 280K

⁦1%⁩ of budget

Progress

⁦1%⁩

Planned ⁦1%⁩

Estimate at completion

SAR 28M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationPhase ⁦3⁩ of ⁦11⁩

Next gate:Planning6 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
  4. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
3On track
2At risk
0Late
Average delay16 days
Jan 27Apr 27Jul 27Oct 27Jan 28
Contractual
Build completePlanned: ⁦2027-07-18⁩Forecast / actual: ⁦2027-08-02⁩Delay: 15 daysG3 +15
Executive
Project plan approvedPlanned: ⁦2026-12-23⁩Forecast / actual: ⁦2027-01-24⁩Delay: 32 daysG1 +32
Payment
Final handoverPlanned: ⁦2027-12-31⁩Forecast / actual: ⁦2028-01-01⁩Delay: 1 dayG5 +1
Regulatory
Testing & acceptance completePlanned: ⁦2027-10-09⁩Forecast / actual: ⁦2027-10-17⁩Delay: 8 daysG4 +8
Project
Designs approvedPlanned: ⁦2027-03-16⁩Forecast / actual: ⁦2027-04-10⁩Delay: 25 daysG2 +25

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-12-23⁩⁦2027-01-24⁩⁦+32⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saAt risk0Not requested
Designs approvedMS-G2Project⁦2027-03-16⁩⁦2027-04-10⁩⁦+25⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saAt risk0Not requested
Build completeMS-G3Contractual⁦2027-07-18⁩⁦2027-08-02⁩⁦+15⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saOn track0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-10-09⁩⁦2027-10-17⁩⁦+8⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saOn track0Not requested
Final handoverMS-G5Payment⁦2027-12-31⁩⁦2028-01-01⁩⁦+1⁩ daysRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Deliverable flow

Pick a stage to filter the register
⁦6⁩ results
Export CSV
Deliverable: Project plan & baseline023-D1SubmittedRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saFaisal A. Al-Shehri⁦2026-11-11⁩V1⁦1⁩ of ⁦2⁩
Deliverable: Monitoring & reporting023-D2DraftFaisal A. Al-ShehriFaisal A. Al-ShehriDigital Transformation Portfolio ManagerP-003f.alshehri@alwaha.gov.saFaisal A. Al-Shehri⁦2026-12-23⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Business requirements023-D3DraftFaisal A. Al-ShehriFaisal A. Al-ShehriDigital Transformation Portfolio ManagerP-003f.alshehri@alwaha.gov.saFaisal A. Al-Shehri⁦2027-02-02⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Solution design023-D4DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVP, Digital Transformation & TechnologyP-011m.alrasheed@alwaha.gov.saFaisal A. Al-Shehri⁦2027-03-16⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Release 1023-D5DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVP, Digital Transformation & TechnologyP-011m.alrasheed@alwaha.gov.saFaisal A. Al-Shehri⁦2027-04-26⁩V0⁦0⁩ of ⁦2⁩
Deliverable: Release 2023-D6DraftRahaf I. Al-NefaieRahaf I. Al-NefaieDirector, Data & AIP-027r.alnefaie@alwaha.gov.saFaisal A. Al-Shehri⁦2027-06-07⁩V0⁦0⁩ of ⁦2⁩
⁦1⁩–⁦6⁩ of ⁦6⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close