10My actionsNotifications
PRJ-2026-023On track3InitiationAgile

Analytics & AI Platform

Add to watchlist

A unified data platform to run AI models that forecast demand for services.

Budget (BAC)

SAR 28M

Actual cost

SAR 280K

⁦1%⁩ of budget

Progress

⁦1%⁩

Planned ⁦1%⁩

Estimate at completion

SAR 28M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationPhase ⁦3⁩ of ⁦11⁩

Next gate:Planning6 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
  4. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 28M split into spent, committed and left, with the estimate at completion

EAC SAR 28M
Revised request SAR 28M
  • Actual spendSAR 280K
  • Committed, not spentSAR 320K
  • Allotted, uncommittedSAR 26.6M
  • Contingency availableSAR 840K

Budget

Original budgetwhen the first baseline was approved
SAR 28M
Approved budgetafter approved change requests
SAR 28M
Current budgetavailable to spend now
SAR 28M
Revised budgetif the pending changes are approved
SAR 28M

Commitments

Commitmentssigned contracts and purchase orders
SAR 600K
Contracts0 active contracts
SAR 0
Purchase orders⁦0⁩ orders
SAR 600K
Remaining budgetapproved less actual
SAR 27.7M

Spend & outlook

Actual costincluding accruals
SAR 280K
Accrualswork done, not yet invoiced
SAR 11K
Estimate at completionthe PM’s bottom-up forecast
SAR 28M
ContingencySAR 560K drawn of SAR 1.4M
SAR 840K

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 560K drawn of SAR 1.4M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 560K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance2.170.300.282.20⁦−0.03⁩
2Analysis & design4.620.060.004.69⁦−0.07⁩
3Build10.860.130.0011.03⁦−0.17⁩
4Testing & acceptance5.430.070.005.52⁦−0.09⁩
5Launch & handover4.070.050.004.14⁦−0.06⁩
Unallocated contingency0.840.000.000.42⁦+0.42⁩
Total28.000.600.2828.00⁦+0.00⁩

Budget split

WBS

SAR 28M

Budget

  • Management & governanceSAR 2.2M⁦8%⁩
  • Analysis & designSAR 4.6M⁦16%⁩
  • BuildSAR 10.9M⁦39%⁩
  • Testing & acceptanceSAR 5.4M⁦19%⁩
  • Launch & handoverSAR 4.1M⁦15%⁩
  • Unallocated contingencySAR 840K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-08-20⁩+598

SPI(t) ⁦0.45⁩ against the approved finish ⁦2027-12-31⁩

Planned valuePV
SAR 1.2M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 280K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 280K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 28M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.92⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.23
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 28M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 27.7M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 28M
  • If the rest goes to planSAR 28M
  • At cost and schedule performanceSAR 119.4M
  • The PM’s bottom-up estimateSAR 28M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 28M

Variance at completion: ⁦+0.00⁩ SAR M

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close