AI Judicial Assistant
Add to watchlistAn AI assistant that summarises case files, suggests precedents from the judicial codices and helps judges and clerks draft.
Budget (BAC)
Actual cost
1% of budget
Progress
Planned 1%
Estimate at completion
SPI · CPI
Forecast finish
On baseline
InitiationPhase 3 of 11
Next gate:Planning6 September 2026
- Idea · CompleteIdea · Complete
- Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
- Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
- Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
- Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
- Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
- Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
- Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+1 days vs approved
- Critical activities
- 12
- of 16 open activities
- Late activities
- 11
- past their baseline finish
- Schedule performance
- 0.23
- earned ÷ planned value
- Next milestone
- in 88 days
- Project plan approved
- Activities (forecast)
- Baseline
- Slip past baseline
- Critical
- Milestone
- Phase / element
- Today
22 rows shown · Data date 2026-10-28
AI schedule analysis
Computed from the current plan: 16 open activities, data date 2026-10-28
“Project plan & baseline” needs a pace 3.1× faster than it has kept
It earned 25% in 52 days; the forecast assumes the rest in 50 days. At the pace so far it finishes on 2027-04-02.
The critical chain
In date order, to final acceptance