PRJ-2026-023On track3InitiationAgile

AI Judicial Assistant

Add to watchlist

An AI assistant that summarises case files, suggests precedents from the judicial codices and helps judges and clerks draft.

Budget (BAC)

SAR 28M

Actual cost

SAR 280K

⁦1%⁩ of budget

Progress

⁦1%⁩

Planned ⁦1%⁩

Estimate at completion

SAR 28M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

InitiationPhase ⁦3⁩ of ⁦11⁩

Next gate:Planning6 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionGoDate20 March 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate8 July 2026Initiation · Current phaseInitiation · Current phase
  4. Gate into «Planning»DecisionNot held yetDate6 September 2026Planning · Not startedPlanning · Not started
  5. Gate into «Approval»DecisionNot held yetApproval · Not startedApproval · Not started
  6. Gate into «Procurement»DecisionNot held yetProcurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+1⁩ days vs approved

Original baseline⁦2027-12-31⁩
Approved baseline⁦2027-12-31⁩
Current forecast⁦2028-01-01⁩
By earned schedule⁦2029-08-20⁩
Critical activities
12
of ⁦16⁩ open activities
Late activities
11
past their baseline finish
Schedule performance
0.23
earned ÷ planned value
Next milestone
in 88 days
Project plan approved
Expand allCollapse all
Activity
AI Judicial AssistantPlanned: ⁦2026-09-06⁩ → ⁦2027-12-31⁩Forecast: ⁦2026-09-06⁩ → ⁦2028-01-01⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2026-09-06⁩ → ⁦2026-12-23⁩Forecast: ⁦2026-09-06⁩ → ⁦2027-01-24⁩Float: ⁦0⁩d
Project plan & baselinePlanned: ⁦2026-09-06⁩ → ⁦2026-11-11⁩Forecast: ⁦2026-09-06⁩ → ⁦2026-12-17⁩Float: ⁦0⁩d+36
Monitoring & reportingPlanned: ⁦2026-10-17⁩ → ⁦2026-12-23⁩Forecast: ⁦2026-11-24⁩ → ⁦2027-01-24⁩Float: ⁦0⁩d+32
Project plan approvedPlanned: ⁦2026-12-23⁩ → ⁦2026-12-23⁩Forecast: ⁦2027-01-24⁩ → ⁦2027-01-24⁩Float: ⁦342⁩dProject plan approved
Analysis & designPlanned: ⁦2026-11-28⁩ → ⁦2027-03-16⁩Forecast: ⁦2027-01-01⁩ → ⁦2027-04-10⁩Float: ⁦0⁩d
Business requirementsPlanned: ⁦2026-11-28⁩ → ⁦2027-02-02⁩Forecast: ⁦2027-01-01⁩ → ⁦2027-03-03⁩Float: ⁦0⁩d+29
Solution designPlanned: ⁦2027-01-08⁩ → ⁦2027-03-16⁩Forecast: ⁦2027-02-08⁩ → ⁦2027-04-10⁩Float: ⁦0⁩d+25
Designs approvedPlanned: ⁦2027-03-16⁩ → ⁦2027-03-16⁩Forecast: ⁦2027-04-10⁩ → ⁦2027-04-10⁩Float: ⁦266⁩dDesigns approved
BuildPlanned: ⁦2027-02-19⁩ → ⁦2027-07-18⁩Forecast: ⁦2027-03-18⁩ → ⁦2027-08-02⁩Float: ⁦0⁩d
Release 1Planned: ⁦2027-02-19⁩ → ⁦2027-04-26⁩Forecast: ⁦2027-03-18⁩ → ⁦2027-05-18⁩Float: ⁦0⁩d+22
Release 2Planned: ⁦2027-04-01⁩ → ⁦2027-06-07⁩Forecast: ⁦2027-04-25⁩ → ⁦2027-06-25⁩Float: ⁦0⁩d+18
IntegrationsPlanned: ⁦2027-05-13⁩ → ⁦2027-07-18⁩Forecast: ⁦2027-06-02⁩ → ⁦2027-08-02⁩Float: ⁦0⁩d+15
Build completePlanned: ⁦2027-07-18⁩ → ⁦2027-07-18⁩Forecast: ⁦2027-08-02⁩ → ⁦2027-08-02⁩Float: ⁦152⁩dBuild complete
Testing & acceptancePlanned: ⁦2027-06-23⁩ → ⁦2027-10-09⁩Forecast: ⁦2027-07-10⁩ → ⁦2027-10-17⁩Float: ⁦0⁩d
System testingPlanned: ⁦2027-06-23⁩ → ⁦2027-08-29⁩Forecast: ⁦2027-07-10⁩ → ⁦2027-09-09⁩Float: ⁦0⁩d+11
User acceptance testingPlanned: ⁦2027-08-04⁩ → ⁦2027-10-09⁩Forecast: ⁦2027-08-17⁩ → ⁦2027-10-17⁩Float: ⁦0⁩d+8
Testing & acceptance completePlanned: ⁦2027-10-09⁩ → ⁦2027-10-09⁩Forecast: ⁦2027-10-17⁩ → ⁦2027-10-17⁩Float: ⁦76⁩dTesting & acceptance complete
Launch & handoverPlanned: ⁦2027-09-14⁩ → ⁦2027-12-31⁩Forecast: ⁦2027-09-24⁩ → ⁦2028-01-01⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2027-09-14⁩ → ⁦2027-11-20⁩Forecast: ⁦2027-09-24⁩ → ⁦2027-11-24⁩Float: ⁦0⁩d+4
Go-live & handoverPlanned: ⁦2027-10-26⁩ → ⁦2027-12-31⁩Forecast: ⁦2027-11-01⁩ → ⁦2028-01-01⁩Float: ⁦0⁩d+1
Final handoverPlanned: ⁦2027-12-31⁩ → ⁦2027-12-31⁩Forecast: ⁦2028-01-01⁩ → ⁦2028-01-01⁩Float: ⁦0⁩dFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦16⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦11⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Unrealistic durations⁦78%⁩ confidence

“Project plan & baseline” needs a pace ⁦3.1⁩× faster than it has kept

It earned ⁦25%⁩ in 52 days; the forecast assumes the rest in 50 days. At the pace so far it finishes on ⁦2027-04-02⁩.

The critical chain

In date order, to final acceptance