Remote Video Hearings Roll-out — Makkah Region

Add to watchlist

Equip 180 courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

ApprovalPhase ⁦5⁩ of ⁦11⁩

Next gate:Procurement20 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate13 February 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 August 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 September 2026Approval · Current phaseApproval · Current phase
  6. Gate into «Procurement»DecisionNot held yetDate20 September 2026Procurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Board of Grievances

Project charter

Remote Video Hearings Roll-out — Makkah Region

APPROVEDV2Approved ⁦2026-07-31⁩

1Project identity

Project name
Remote Video Hearings Roll-out — Makkah Region
Project code
PRJ-2026-022
Sponsor
Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedVice President, Judicial AffairsP-011m.alrasheed@bog.gov.sa
Project manager
Eng. Yasser M. Al-ZahraniEng. Yasser M. Al-ZahraniDirector, CybersecurityP-026y.alzahrani@bog.gov.sa
Business owner
Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Judicial FacilitiesP-013b.alshammari@bog.gov.sa
Portfolio & programme
Judicial Complexes & Smart Courts PortfolioSmart Courts Programme
Type & methodology
Infrastructure · Stage-Gate
Current phase
5Approval

2Background & rationale

Equip ⁦180⁩ courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.

3Objectives

  1. 1Raise the quality of beneficiary service and the courthouse experience
  2. 2Make administrative justice accessible through fit-for-purpose courts in every region

4Scope

In scope

  • Equip ⁦180⁩ courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.
  • Saudi Building Code compliance
  • An approved plan to keep the courts sitting during the works

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

  1. 1Saudi Building Code compliance
  2. 2An approved plan to keep the courts sitting during the works
  3. 3Civil-defence requirements

6Deliverables

1Project management plan⁦2026-08-26⁩
2Main deliverable — stage 1⁦2027-06-08⁩
3Main deliverable — final stage⁦2028-01-06⁩
4Final report⁦2028-03-31⁩

7Key milestones

  1. Charter approved⁦2026-07-31⁩
  2. Contract signed⁦2026-11-07⁩
  3. 50% of works complete⁦2027-06-08⁩
  4. Provisional acceptance⁦2028-02-11⁩
  5. Closure⁦2028-03-31⁩

8Budget

  • Main contract⁦72.0%⁩33.1M
  • Supervision & consulting⁦14.1%⁩6.5M
  • Internal team⁦8.9%⁩4.1M
  • Contingency reserve (⁦5%⁩)⁦5.0%⁩2.3M
The owning sector’s approved budgetTotal46M

9Timeline

Start
2026-08-0219 Safar 1448 AH
Baseline finish
2028-03-315 Dhuʻl-Qiʻdah 1449 AH
Duration
⁦20⁩ months

10Key risks

  • MediumPrivacy requirements for video-hearing recordings under the Personal Data Protection Law

11Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

  • Named internal staff available throughout
  • Approvals land within workflow SLAs

13Stakeholders

  • Project sponsorDecisions and funding
  • Business ownerAccepts deliverables, owns benefits
  • Projects Follow-up Office (EPMO)Governance and compliance

14Success criteria

  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • EPMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, issues, weekly statusWeekly