PRJ-2026-022On track5ApprovalStage-Gate

Remote Video Hearings Roll-out — Makkah Region

Add to watchlist

Equip 180 courtrooms and circuit offices in Jeddah, Makkah and Taif for video hearings with secure recording.

Budget (BAC)

SAR 46M

Actual cost

SAR 920K

⁦2%⁩ of budget

Progress

⁦2%⁩

Planned ⁦2%⁩

Estimate at completion

SAR 46M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-03-31⁩

On baseline

ApprovalPhase ⁦5⁩ of ⁦11⁩

Next gate:Procurement20 September 2026

  1. Idea · CompleteIdea · Complete
  2. Gate into «Feasibility»DecisionConditional goDate13 February 2026Feasibility · CompleteFeasibility · Complete
  3. Gate into «Initiation»DecisionGoDate3 June 2026Initiation · CompleteInitiation · Complete
  4. Gate into «Planning»DecisionGoDate2 August 2026Planning · CompletePlanning · Complete
  5. Gate into «Approval»DecisionConditional goDate1 September 2026Approval · Current phaseApproval · Current phase
  6. Gate into «Procurement»DecisionNot held yetDate20 September 2026Procurement · Not startedProcurement · Not started
  7. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  8. Gate into «Monitoring & Control»DecisionNot held yetMonitoring & Control · Not startedMonitoring & Control · Not started
  9. Gate into «Handover»DecisionNot held yetHandover · Not startedHandover · Not started
  10. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
  11. Gate into «Benefits Realization»DecisionNot held yetBenefits Realization · Not startedBenefits Realization · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 46M split into spent, committed and left, with the estimate at completion

EAC SAR 46M
Revised request SAR 46M
  • Actual spendSAR 920K
  • Committed, not spentSAR 180K
  • Allotted, uncommittedSAR 43.5M
  • Contingency availableSAR 1.4M

Budget

Original budgetwhen the first baseline was approved
SAR 46M
Approved budgetafter approved change requests
SAR 46M
Current budgetavailable to spend now
SAR 46M
Revised budgetif the pending changes are approved
SAR 46M

Commitments

Commitmentssigned contracts and purchase orders
SAR 1.1M
Contracts0 active contracts
SAR 0
Purchase orders⁦0⁩ orders
SAR 1.1M
Remaining budgetapproved less actual
SAR 45.1M

Spend & outlook

Actual costincluding accruals
SAR 920K
Accrualswork done, not yet invoiced
SAR 37K
Estimate at completionthe PM’s bottom-up forecast
SAR 46M
ContingencySAR 920K drawn of SAR 2.3M
SAR 1.4M

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 920K drawn of SAR 2.3M

  • Covering realised delivery risks⁦2026-08-29⁩SAR 920K

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance2.680.930.922.71⁦−0.03⁩
2Design & permits5.350.020.005.44⁦−0.08⁩
3Civil works16.960.070.0017.22⁦−0.27⁩
4MEP works13.390.060.0013.60⁦−0.21⁩
5Handover6.250.030.006.35⁦−0.10⁩
Unallocated contingency1.380.000.000.69⁦+0.69⁩
Total46.001.100.9246.00⁦+0.00⁩

Budget split

WBS

SAR 46M

Budget

  • Management & governanceSAR 2.7M⁦6%⁩
  • Design & permitsSAR 5.4M⁦12%⁩
  • Civil worksSAR 17M⁦37%⁩
  • MEP worksSAR 13.4M⁦29%⁩
  • HandoverSAR 6.2M⁦14%⁩
  • Unallocated contingencySAR 1.4M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2029-09-03⁩+521

SPI(t) ⁦0.54⁩ against the approved finish ⁦2028-03-31⁩

Planned valuePV
SAR 2.8M
The value of the work that should be done by today.
PV
Earned valueEV
SAR 920K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 920K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 46M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−1.88⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.33
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 46M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 45.1M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 46M
  • If the rest goes to planSAR 46M
  • At cost and schedule performanceSAR 137.9M
  • The PM’s bottom-up estimateSAR 46M
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 46M

Variance at completion: ⁦+0.00⁩ SAR M